Prime Gardens construction progress

The register lists Prime Gardens in Arjan as complete, with a registered completion date of April 2024. Its last site inspection on record was in April 2024. The developer is Prescott Real Estate Development.

100%

Built, at the site inspection of 19 April 2024

Construction complete

Registered completion date
April 2024
Construction started
June 2022
First registered
June 2022
Community
Arjan
Units
139
Escrow bank
Mashreq Bank
Name in Arabic
بريم جاردنز
Project number
2416
Site inspections
6

Schedule

The register lists Prime Gardens as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20232024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 April 2024

100%+20 pts

  • Prime Gardens construction site, inspection photo 1, 19 April 2024
  • Prime Gardens construction site, inspection photo 2, 19 April 2024
  • Prime Gardens construction site, inspection photo 3, 19 April 2024
  • Prime Gardens construction site, inspection photo 4, 19 April 2024

15 November 2023

80%+30 pts

  • Prime Gardens construction site, inspection photo 1, 15 November 2023
  • Prime Gardens construction site, inspection photo 2, 15 November 2023
  • Prime Gardens construction site, inspection photo 3, 15 November 2023
  • Prime Gardens construction site, inspection photo 4, 15 November 2023

15 June 2023

51%+22 pts

  • Prime Gardens construction site, inspection photo 1, 15 June 2023
  • Prime Gardens construction site, inspection photo 2, 15 June 2023
  • Prime Gardens construction site, inspection photo 3, 15 June 2023
  • Prime Gardens construction site, inspection photo 4, 15 June 2023

1 March 2023

28%+8.4 pts

  • Prime Gardens construction site, inspection photo 1, 1 March 2023
  • Prime Gardens construction site, inspection photo 2, 1 March 2023
  • Prime Gardens construction site, inspection photo 3, 1 March 2023
  • Prime Gardens construction site, inspection photo 4, 1 March 2023

5 January 2023

20%+12 pts

  • Prime Gardens construction site, inspection photo 1, 5 January 2023
  • Prime Gardens construction site, inspection photo 2, 5 January 2023
  • Prime Gardens construction site, inspection photo 3, 5 January 2023
  • Prime Gardens construction site, inspection photo 4, 5 January 2023

24 October 2022

8.5%

  • Prime Gardens construction site, inspection photo 1, 24 October 2022
  • Prime Gardens construction site, inspection photo 2, 24 October 2022
  • Prime Gardens construction site, inspection photo 3, 24 October 2022
  • Prime Gardens construction site, inspection photo 4, 24 October 2022

All 45 site photos, by inspection date

Context

Arjan has 23 projects under construction, 48% built on average.

Prescott Real Estate Development has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Prime Gardens?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Prime Gardens handover date?
Construction of Prime Gardens is recorded as complete, with a registered completion date of April 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Prime Gardens?
Prime Gardens was 100% built at the site inspection on 19 April 2024. The site has been inspected 6 times since October 2022. The Land Department took 45 site photos at its inspections.
Is Prime Gardens delayed?
The register lists construction as complete.
Who is building Prime Gardens?
The registered developer is Prescott Real Estate Development. It has 6 other projects under construction in Dubai.
Which bank holds the escrow account for Prime Gardens?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.