Levanto By Oro24 construction progress

Levanto By Oro24 in Jumeirah Village Circle is 66% built at the Land Department inspection of September 2026. Developer Oro24 Real Estate Development. Completion registered for December 2025.

66%

Built, at the Land Department site inspection of 9 September 2026

10 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
August 2027
Construction started
December 2022
Registered with the Land Department
November 2022
Units
579
Escrow bank
Mashreq Bank
Name in Arabic
ليفانتو من أورو 24
Land Department project number
2517
Land Department site inspections
13

Schedule

Levanto By Oro24 was registered to complete in December 2025, 10 months ago, and is still under construction. Over the last year of inspections it has added about 3.2 points a month. Kept at that rate, the site would reach 100% around August 2027.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 September 2026

66%+5.6 pts

  • Levanto By Oro24 construction site, Land Department inspection photo 1, 9 September 2026
  • Levanto By Oro24 construction site, Land Department inspection photo 2, 9 September 2026
  • Levanto By Oro24 construction site, Land Department inspection photo 3, 9 September 2026
  • Levanto By Oro24 construction site, Land Department inspection photo 4, 9 September 2026

10 July 2026

60%+4.7 pts

  • Levanto By Oro24 construction site, Land Department inspection photo 1, 10 July 2026
  • Levanto By Oro24 construction site, Land Department inspection photo 2, 10 July 2026
  • Levanto By Oro24 construction site, Land Department inspection photo 3, 10 July 2026
  • Levanto By Oro24 construction site, Land Department inspection photo 4, 10 July 2026

23 April 2026

56%+9.6 pts

  • Levanto By Oro24 construction site, Land Department inspection photo 1, 23 April 2026
  • Levanto By Oro24 construction site, Land Department inspection photo 2, 23 April 2026
  • Levanto By Oro24 construction site, Land Department inspection photo 3, 23 April 2026
  • Levanto By Oro24 construction site, Land Department inspection photo 4, 23 April 2026

29 January 2026

46%+17 pts

  • Levanto By Oro24 construction site, Land Department inspection photo 1, 29 January 2026
  • Levanto By Oro24 construction site, Land Department inspection photo 2, 29 January 2026
  • Levanto By Oro24 construction site, Land Department inspection photo 3, 29 January 2026
  • Levanto By Oro24 construction site, Land Department inspection photo 4, 29 January 2026

19 September 2025

29%+4.1 pts

  • Levanto By Oro24 construction site, Land Department inspection photo 1, 19 September 2025
  • Levanto By Oro24 construction site, Land Department inspection photo 2, 19 September 2025
  • Levanto By Oro24 construction site, Land Department inspection photo 3, 19 September 2025
  • Levanto By Oro24 construction site, Land Department inspection photo 4, 19 September 2025

27 May 2025

25%+8.9 pts

  • Levanto By Oro24 construction site, Land Department inspection photo 1, 27 May 2025
  • Levanto By Oro24 construction site, Land Department inspection photo 2, 27 May 2025
  • Levanto By Oro24 construction site, Land Department inspection photo 3, 27 May 2025
  • Levanto By Oro24 construction site, Land Department inspection photo 4, 27 May 2025

27 December 2024

16%+8.5 pts

  • Levanto By Oro24 construction site, Land Department inspection photo 1, 27 December 2024
  • Levanto By Oro24 construction site, Land Department inspection photo 2, 27 December 2024
  • Levanto By Oro24 construction site, Land Department inspection photo 3, 27 December 2024
  • Levanto By Oro24 construction site, Land Department inspection photo 4, 27 December 2024

30 September 2024

7.6%+4.7 pts

  • Levanto By Oro24 construction site, Land Department inspection photo 1, 30 September 2024
  • Levanto By Oro24 construction site, Land Department inspection photo 2, 30 September 2024
  • Levanto By Oro24 construction site, Land Department inspection photo 3, 30 September 2024
  • Levanto By Oro24 construction site, Land Department inspection photo 4, 30 September 2024

20 March 2024

2.9%+0.9 pts

  • Levanto By Oro24 construction site, Land Department inspection photo 1, 20 March 2024
  • Levanto By Oro24 construction site, Land Department inspection photo 2, 20 March 2024
  • Levanto By Oro24 construction site, Land Department inspection photo 3, 20 March 2024
  • Levanto By Oro24 construction site, Land Department inspection photo 4, 20 March 2024

26 September 2023

2.0%+1.3 pts

  • Levanto By Oro24 construction site, Land Department inspection photo 1, 26 September 2023
  • Levanto By Oro24 construction site, Land Department inspection photo 2, 26 September 2023
  • Levanto By Oro24 construction site, Land Department inspection photo 3, 26 September 2023
  • Levanto By Oro24 construction site, Land Department inspection photo 4, 26 September 2023

All 109 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Oro24 Real Estate Development has 4 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Levanto By Oro24?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Levanto By Oro24 be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around August 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Levanto By Oro24 is built?
66%, measured at the Land Department site inspection on 9 September 2026. The Land Department engineers have inspected the site 13 times since November 2022.
Is Levanto By Oro24 delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building Levanto By Oro24?
The registered developer is Oro24 Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Levanto By Oro24?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.