Elano By Oro24 construction photos

61 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of Elano By Oro24 was built on the day of each visit.

11 September 202670% built

24 April 202656% built

22 January 202640% built

6 October 202532% built

27 May 202522% built

20 March 20243.8% built

6 November 20232.7% built

1 August 20230.2% built

Back to Elano By Oro24 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.