Sparklz By Danube construction photos
18 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of Sparklz By Danube was built on the day of each visit.
25 August 20267.8% built
12 May 20263.8% built
10 March 20260.5% built
2 October 20250.1% built
19 March 20250% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.