Nuve By Zoya construction progress
Nuve By Zoya is 0.8% built at the Land Department inspection of July 2026. Developer Zoya One Real Estate Developments. Completion registered for June 2028.
0.8%
Built, at the Land Department site inspection of 20 July 2026
Running behind its date
- Completion date (Land Department)
- June 2028
- Finish at recent pace
- November 2090
- Construction started
- April 2026
- Registered with the Land Department
- February 2026
- Developer
- Zoya One Real Estate Developments
- Units
- 234
- Escrow bank
- Emirates NBD
- Name in Arabic
- نوفي باي زويا
- Land Department project number
- 4290
- Land Department site inspections
- 2
Schedule
Between January 2026 and July 2026 the site added about 0.1 points a month. At that rate it would finish around November 2090, more than three months after the June 2028 date registered with the Land Department.
Site inspections
20 July 2026
0.8%+0.8 pts
14 January 2026
0%
Context
Zoya One Real Estate Developments has 6 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Nuve By Zoya?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Nuve By Zoya be completed?
- The completion date registered with the Dubai Land Department is June 2028. At the pace of its recent inspections the site would reach 100% around November 2090. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Nuve By Zoya is built?
- 0.8%, measured at the Land Department site inspection on 20 July 2026. The Land Department engineers have inspected the site 2 times since January 2026.
- Is Nuve By Zoya delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Nuve By Zoya?
- The registered developer is Zoya One Real Estate Developments. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Nuve By Zoya?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Pristine By ZoyaAlso by Zoya One Real Estate Developments. 58%, Due January 2027.
- Miorah By ZoyaAlso by Zoya One Real Estate Developments. 16%, Due August 2027.
- Izel By ZoyaAlso by Zoya One Real Estate Developments. 0%.
- Elanora By ZoyaAlso by Zoya One Real Estate Developments. 0%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.