Miorah By Zoya construction progress

Miorah By Zoya is 16% built at the Land Department inspection of July 2026. Developer Zoya One Real Estate Developments. Completion registered for August 2027.

16%

Built, at the Land Department site inspection of 20 July 2026

Running behind its date

Completion date (Land Department)
August 2027
Finish at recent pace
November 2029
Construction started
December 2025
Registered with the Land Department
January 2026
Units
60
Escrow bank
Emirates NBD
Name in Arabic
ميورا باي زويا
Land Department project number
4228
Land Department site inspections
3

Schedule

Between November 2025 and July 2026 the site added about 2.1 points a month. At that rate it would finish around November 2029, more than three months after the August 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 July 2026

16%+9.2 pts

  • Miorah By Zoya construction site, Land Department inspection photo 1, 20 July 2026
  • Miorah By Zoya construction site, Land Department inspection photo 2, 20 July 2026
  • Miorah By Zoya construction site, Land Department inspection photo 3, 20 July 2026
  • Miorah By Zoya construction site, Land Department inspection photo 4, 20 July 2026

6 May 2026

6.9%+6.9 pts

  • Miorah By Zoya construction site, Land Department inspection photo 1, 6 May 2026
  • Miorah By Zoya construction site, Land Department inspection photo 2, 6 May 2026
  • Miorah By Zoya construction site, Land Department inspection photo 3, 6 May 2026
  • Miorah By Zoya construction site, Land Department inspection photo 4, 6 May 2026

26 November 2025

0%

  • Miorah By Zoya construction site, Land Department inspection photo 1, 26 November 2025
  • Miorah By Zoya construction site, Land Department inspection photo 2, 26 November 2025
  • Miorah By Zoya construction site, Land Department inspection photo 3, 26 November 2025

All 12 site photos, by inspection date

Context

Zoya One Real Estate Developments has 6 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Miorah By Zoya?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Miorah By Zoya be completed?
The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around November 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Miorah By Zoya is built?
16%, measured at the Land Department site inspection on 20 July 2026. The Land Department engineers have inspected the site 3 times since November 2025.
Is Miorah By Zoya delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Miorah By Zoya?
The registered developer is Zoya One Real Estate Developments. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Miorah By Zoya?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.