Miorah By Zoya construction progress
The registered completion date for Miorah By Zoya is August 2027. At the last site inspection, in July 2026, it was 16% built. The developer is Zoya One Real Estate Developments.
16%
Built, at the site inspection of 20 July 2026
Running behind its date
- Registered completion date
- August 2027
- Finish at recent pace
- November 2029
- Construction started
- December 2025
- First registered
- January 2026
- Developer
- Zoya One Real Estate Developments
- Units
- 60
- Escrow bank
- Emirates NBD
- Name in Arabic
- ميورا باي زويا
- Project number
- 4228
- Site inspections
- 3
Schedule
Between November 2025 and July 2026 the site added about 2.1 points a month. At that rate it would finish around November 2029, more than three months after its registered date of August 2027.
Site inspections
20 July 2026
16%+9.2 pts
6 May 2026
6.9%+6.9 pts
26 November 2025
0%
Context
Zoya One Real Estate Developments has 10 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Miorah By Zoya?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Miorah By Zoya handover date?
- The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Miorah By Zoya?
- Miorah By Zoya was 16% built at the site inspection on 20 July 2026. The site has been inspected 3 times since November 2025. The Land Department took 12 site photos at its inspections.
- Is Miorah By Zoya delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
- Who is building Miorah By Zoya?
- The registered developer is Zoya One Real Estate Developments. It has 9 other projects under construction in Dubai.
- Which bank holds the escrow account for Miorah By Zoya?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Pristine By ZoyaAlso by Zoya One Real Estate Developments. 58%, Due January 2027.
- Nuve By ZoyaAlso by Zoya One Real Estate Developments. 0.8%, Due June 2028.
- Izel By ZoyaAlso by Zoya One Real Estate Developments. 0%, Due September 2028.
- Elanora By ZoyaAlso by Zoya One Real Estate Developments. 0%, Due March 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)





