Arabian Ranches Lll - Elie Saab construction progress

The register lists Arabian Ranches Lll - Elie Saab in Wadi Al Safa 5 as complete, with a registered completion date of September 2025. Its last site inspection on record was in September 2025. The developer is Emaar Development.

100%

Built, at the site inspection of 10 September 2025

Construction complete

Registered completion date
September 2025
Construction started
March 2022
First registered
October 2021
Units
129
Escrow bank
Dubai Islamic Bank
Name in Arabic
المرابع العربية ااا - ايلي صعب
Project number
2311
Site inspections
9

Schedule

The register lists Arabian Ranches Lll - Elie Saab as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 September 2025

100%+2.7 pts

  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 1, 10 September 2025
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 2, 10 September 2025
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 3, 10 September 2025
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 4, 10 September 2025

2 July 2025

97%+6.9 pts

  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 1, 2 July 2025
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 2, 2 July 2025
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 3, 2 July 2025
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 4, 2 July 2025

17 January 2025

90%+24 pts

  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 1, 17 January 2025
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 2, 17 January 2025
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 3, 17 January 2025
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 4, 17 January 2025

16 September 2024

67%+20 pts

  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 1, 16 September 2024
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 2, 16 September 2024
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 3, 16 September 2024
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 4, 16 September 2024

9 May 2024

46%+24 pts

  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 1, 9 May 2024
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 2, 9 May 2024
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 3, 9 May 2024
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 4, 9 May 2024

17 October 2023

22%+17 pts

  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 1, 17 October 2023
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 2, 17 October 2023
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 3, 17 October 2023
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 4, 17 October 2023

6 June 2023

5.4%+4.4 pts

  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 1, 6 June 2023
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 2, 6 June 2023
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 3, 6 June 2023
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 4, 6 June 2023

28 November 2022

1.0%+0.9 pts

  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 1, 28 November 2022
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 2, 28 November 2022
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 3, 28 November 2022
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 4, 28 November 2022

11 August 2022

0.1%

  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 1, 11 August 2022
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 2, 11 August 2022
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 3, 11 August 2022
  • Arabian Ranches Lll - Elie Saab construction site, inspection photo 4, 11 August 2022

All 69 site photos, by inspection date

Context

Wadi Al Safa 5 has 13 projects under construction, 24% built on average.

Emaar Development has 52 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Arabian Ranches Lll - Elie Saab?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Arabian Ranches Lll - Elie Saab handover date?
Construction of Arabian Ranches Lll - Elie Saab is recorded as complete, with a registered completion date of September 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Arabian Ranches Lll - Elie Saab?
Arabian Ranches Lll - Elie Saab was 100% built at the site inspection on 10 September 2025. The site has been inspected 9 times since August 2022. The Land Department took 69 site photos at its inspections.
Is Arabian Ranches Lll - Elie Saab delayed?
The register lists construction as complete.
Who is building Arabian Ranches Lll - Elie Saab?
The registered developer is Emaar Development. It has 52 other projects under construction in Dubai.
Which bank holds the escrow account for Arabian Ranches Lll - Elie Saab?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.