Silicon Gates 4 construction progress

The register lists Silicon Gates 4 in Silicon Oasis as complete, with a registered completion date of July 2016. Its last site inspection on record was in July 2016. The developer is Time Properties.

100%

Built, at the site inspection of 31 July 2016

Construction complete

Registered completion date
July 2016
Construction started
September 2013
First registered
October 2014
Community
Silicon Oasis
Units
316
Escrow bank
Emirates Islamic Bank
Name in Arabic
سيليكون جيت 4
Project number
775
Site inspections
6

Schedule

The register lists Silicon Gates 4 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201420152016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

31 July 2016

100%+1.9 pts

  • Silicon Gates 4 construction site, inspection photo 1, 31 July 2016
  • Silicon Gates 4 construction site, inspection photo 2, 31 July 2016
  • Silicon Gates 4 construction site, inspection photo 3, 31 July 2016
  • Silicon Gates 4 construction site, inspection photo 4, 31 July 2016

18 May 2016

98%+12 pts

  • Silicon Gates 4 construction site, inspection photo 1, 18 May 2016
  • Silicon Gates 4 construction site, inspection photo 2, 18 May 2016
  • Silicon Gates 4 construction site, inspection photo 3, 18 May 2016
  • Silicon Gates 4 construction site, inspection photo 4, 18 May 2016

19 January 2016

86%+14 pts

  • Silicon Gates 4 construction site, inspection photo 1, 19 January 2016
  • Silicon Gates 4 construction site, inspection photo 2, 19 January 2016
  • Silicon Gates 4 construction site, inspection photo 3, 19 January 2016
  • Silicon Gates 4 construction site, inspection photo 4, 19 January 2016

31 August 2015

71%+16 pts

  • Silicon Gates 4 construction site, inspection photo 1, 31 August 2015
  • Silicon Gates 4 construction site, inspection photo 2, 31 August 2015
  • Silicon Gates 4 construction site, inspection photo 3, 31 August 2015
  • Silicon Gates 4 construction site, inspection photo 4, 31 August 2015

25 March 2015

56%+37 pts

  • Silicon Gates 4 construction site, inspection photo 1, 25 March 2015
  • Silicon Gates 4 construction site, inspection photo 2, 25 March 2015
  • Silicon Gates 4 construction site, inspection photo 3, 25 March 2015
  • Silicon Gates 4 construction site, inspection photo 4, 25 March 2015

3 July 2014

19%

  • Silicon Gates 4 construction site, inspection photo 1, 3 July 2014
  • Silicon Gates 4 construction site, inspection photo 2, 3 July 2014
  • Silicon Gates 4 construction site, inspection photo 3, 3 July 2014
  • Silicon Gates 4 construction site, inspection photo 4, 3 July 2014

All 50 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Time Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Silicon Gates 4?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Silicon Gates 4 handover date?
Construction of Silicon Gates 4 is recorded as complete, with a registered completion date of July 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Silicon Gates 4?
Silicon Gates 4 was 100% built at the site inspection on 31 July 2016. The site has been inspected 6 times since July 2014. The Land Department took 50 site photos at its inspections.
Is Silicon Gates 4 delayed?
The register lists construction as complete.
Who is building Silicon Gates 4?
The registered developer is Time Properties. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Silicon Gates 4?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.