Time 3 construction progress

Time 3 in Dubai Land Residence Complex is 47% built at the Land Department inspection of August 2026. Developer Time Properties. Completion registered for August 2027.

47%

Built, at the Land Department site inspection of 24 August 2026

Running behind its date

Completion date (Land Department)
August 2027
Finish at recent pace
April 2028
Construction started
August 2024
Registered with the Land Department
August 2024
Developer
Time Properties
Units
288
Escrow bank
Emirates Islamic Bank
Name in Arabic
تايم 3
Land Department project number
3155
Land Department site inspections
5

Schedule

Between November 2025 and August 2026 the site added about 2.7 points a month. At that rate it would finish around April 2028, more than three months after the August 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

24 August 2026

47%+14 pts

  • Time 3 construction site, Land Department inspection photo 1, 24 August 2026
  • Time 3 construction site, Land Department inspection photo 2, 24 August 2026
  • Time 3 construction site, Land Department inspection photo 3, 24 August 2026
  • Time 3 construction site, Land Department inspection photo 4, 24 August 2026

27 March 2026

33%+11 pts

  • Time 3 construction site, Land Department inspection photo 1, 27 March 2026
  • Time 3 construction site, Land Department inspection photo 2, 27 March 2026
  • Time 3 construction site, Land Department inspection photo 3, 27 March 2026
  • Time 3 construction site, Land Department inspection photo 4, 27 March 2026

5 November 2025

21%+18 pts

  • Time 3 construction site, Land Department inspection photo 1, 5 November 2025
  • Time 3 construction site, Land Department inspection photo 2, 5 November 2025
  • Time 3 construction site, Land Department inspection photo 3, 5 November 2025
  • Time 3 construction site, Land Department inspection photo 4, 5 November 2025

15 April 2025

2.9%+2.9 pts

  • Time 3 construction site, Land Department inspection photo 1, 15 April 2025
  • Time 3 construction site, Land Department inspection photo 2, 15 April 2025
  • Time 3 construction site, Land Department inspection photo 3, 15 April 2025
  • Time 3 construction site, Land Department inspection photo 4, 15 April 2025

26 July 2024

0%

  • Time 3 construction site, Land Department inspection photo 1, 26 July 2024
  • Time 3 construction site, Land Department inspection photo 2, 26 July 2024

All 26 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average. Time 3 is ahead of that average.

Time Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Time 3?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Time 3 be completed?
The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Time 3 is built?
47%, measured at the Land Department site inspection on 24 August 2026. The Land Department engineers have inspected the site 5 times since July 2024.
Is Time 3 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Time 3?
The registered developer is Time Properties. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Time 3?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.