Time 3 construction progress
Time 3 in Dubai Land Residence Complex is 47% built at the Land Department inspection of August 2026. Developer Time Properties. Completion registered for August 2027.
47%
Built, at the Land Department site inspection of 24 August 2026
Running behind its date
- Completion date (Land Department)
- August 2027
- Finish at recent pace
- April 2028
- Construction started
- August 2024
- Registered with the Land Department
- August 2024
- Developer
- Time Properties
- Community
- Dubai Land Residence Complex
- Units
- 288
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- تايم 3
- Land Department project number
- 3155
- Land Department site inspections
- 5
Schedule
Between November 2025 and August 2026 the site added about 2.7 points a month. At that rate it would finish around April 2028, more than three months after the August 2027 date registered with the Land Department.
Site inspections
24 August 2026
47%+14 pts
27 March 2026
33%+11 pts
5 November 2025
21%+18 pts
15 April 2025
2.9%+2.9 pts
26 July 2024
0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average. Time 3 is ahead of that average.
Time Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Time 3?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Time 3 be completed?
- The completion date registered with the Dubai Land Department is August 2027. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Time 3 is built?
- 47%, measured at the Land Department site inspection on 24 August 2026. The Land Department engineers have inspected the site 5 times since July 2024.
- Is Time 3 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
- Who is building Time 3?
- The registered developer is Time Properties. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Time 3?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Time 2Also by Time Properties. 87%, Due June 2026, passed.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Samana Ivy GardensNearby in Dubai Land Residence Complex. 41%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.