Time 3 construction progress

The registered completion date for Time 3 in Dubai Land Residence Complex is August 2027. At the last site inspection, in August 2026, it was 47% built. The developer is Time Properties.

47%

Built, at the site inspection of 24 August 2026

Running behind its date

Registered completion date
August 2027
Finish at recent pace
April 2028
Construction started
August 2024
First registered
August 2024
Developer
Time Properties
Units
288
Escrow bank
Emirates Islamic Bank
Name in Arabic
تايم 3
Project number
3155
Site inspections
5

Schedule

Between November 2025 and August 2026 the site added about 2.7 points a month. At that rate it would finish around April 2028, more than three months after its registered date of August 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 August 2026

47%+14 pts

  • Time 3 construction site, inspection photo 1, 24 August 2026
  • Time 3 construction site, inspection photo 2, 24 August 2026
  • Time 3 construction site, inspection photo 3, 24 August 2026
  • Time 3 construction site, inspection photo 4, 24 August 2026

27 March 2026

33%+11 pts

  • Time 3 construction site, inspection photo 1, 27 March 2026
  • Time 3 construction site, inspection photo 2, 27 March 2026
  • Time 3 construction site, inspection photo 3, 27 March 2026
  • Time 3 construction site, inspection photo 4, 27 March 2026

5 November 2025

21%+18 pts

  • Time 3 construction site, inspection photo 1, 5 November 2025
  • Time 3 construction site, inspection photo 2, 5 November 2025
  • Time 3 construction site, inspection photo 3, 5 November 2025
  • Time 3 construction site, inspection photo 4, 5 November 2025

15 April 2025

2.9%+2.9 pts

  • Time 3 construction site, inspection photo 1, 15 April 2025
  • Time 3 construction site, inspection photo 2, 15 April 2025
  • Time 3 construction site, inspection photo 3, 15 April 2025
  • Time 3 construction site, inspection photo 4, 15 April 2025

26 July 2024

0%

  • Time 3 construction site, inspection photo 1, 26 July 2024
  • Time 3 construction site, inspection photo 2, 26 July 2024

All 26 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Time Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Time 3?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Time 3 handover date?
The registered completion date is August 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Time 3?
Time 3 was 47% built at the site inspection on 24 August 2026. The site has been inspected 5 times since July 2024. The Land Department took 26 site photos at its inspections.
Is Time 3 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2027.
Who is building Time 3?
The registered developer is Time Properties. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Time 3?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.