Silicon Gates 4 construction photos
50 photos from 6 site inspections, newest first. The percentage is how much of Silicon Gates 4 was built on the day of each visit.
31 July 2016100% built
18 May 201698% built
19 January 201686% built
31 August 201571% built
25 March 201556% built
3 July 201419% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.