Skip to content

Arabian Gate construction progress

The register lists Arabian Gate in Silicon Oasis as complete, with a registered completion date of October 2020. Its last site inspection on record was in October 2020. The developer is Time Properties.

100%

Built, at the site inspection of 1 October 2020

Construction complete

Registered completion date
October 2020
Construction started
October 2015
First registered
May 2015
Community
Silicon Oasis
Units
716
Escrow bank
Emirates Islamic Bank
Name in Arabic
اريبيان جيت
Project number
1662
Site inspections
11

Schedule

The register lists Arabian Gate as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20162017201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 October 2020

100%+2.0 pts

  • Arabian Gate construction site, inspection photo 1, 1 October 2020
  • Arabian Gate construction site, inspection photo 2, 1 October 2020
  • Arabian Gate construction site, inspection photo 3, 1 October 2020
  • Arabian Gate construction site, inspection photo 4, 1 October 2020

10 June 2020

98%+4.7 pts

  • Arabian Gate construction site, inspection photo 1, 10 June 2020
  • Arabian Gate construction site, inspection photo 2, 10 June 2020
  • Arabian Gate construction site, inspection photo 3, 10 June 2020
  • Arabian Gate construction site, inspection photo 4, 10 June 2020

22 September 2019

93%+5.2 pts

  • Arabian Gate construction site, inspection photo 1, 22 September 2019
  • Arabian Gate construction site, inspection photo 2, 22 September 2019
  • Arabian Gate construction site, inspection photo 3, 22 September 2019
  • Arabian Gate construction site, inspection photo 4, 22 September 2019

13 May 2019

88%+7.7 pts

  • Arabian Gate construction site, inspection photo 1, 13 May 2019
  • Arabian Gate construction site, inspection photo 2, 13 May 2019
  • Arabian Gate construction site, inspection photo 3, 13 May 2019
  • Arabian Gate construction site, inspection photo 4, 13 May 2019

16 January 2019

80%+19 pts

  • Arabian Gate construction site, inspection photo 1, 16 January 2019
  • Arabian Gate construction site, inspection photo 2, 16 January 2019
  • Arabian Gate construction site, inspection photo 3, 16 January 2019
  • Arabian Gate construction site, inspection photo 4, 16 January 2019

5 September 2018

61%+16 pts

  • Arabian Gate construction site, inspection photo 1, 5 September 2018
  • Arabian Gate construction site, inspection photo 2, 5 September 2018
  • Arabian Gate construction site, inspection photo 3, 5 September 2018
  • Arabian Gate construction site, inspection photo 4, 5 September 2018

5 April 2018

46%+15 pts

  • Arabian Gate construction site, inspection photo 1, 5 April 2018
  • Arabian Gate construction site, inspection photo 2, 5 April 2018
  • Arabian Gate construction site, inspection photo 3, 5 April 2018
  • Arabian Gate construction site, inspection photo 4, 5 April 2018

26 October 2017

31%+9.8 pts

  • Arabian Gate construction site, inspection photo 1, 26 October 2017
  • Arabian Gate construction site, inspection photo 2, 26 October 2017
  • Arabian Gate construction site, inspection photo 3, 26 October 2017
  • Arabian Gate construction site, inspection photo 4, 26 October 2017

30 May 2017

21%+9.4 pts

  • Arabian Gate construction site, inspection photo 1, 30 May 2017
  • Arabian Gate construction site, inspection photo 2, 30 May 2017
  • Arabian Gate construction site, inspection photo 3, 30 May 2017
  • Arabian Gate construction site, inspection photo 4, 30 May 2017

8 December 2016

12%+0.0 pts

  • Arabian Gate construction site, inspection photo 1, 8 December 2016
  • Arabian Gate construction site, inspection photo 2, 8 December 2016
  • Arabian Gate construction site, inspection photo 3, 8 December 2016
  • Arabian Gate construction site, inspection photo 4, 8 December 2016

All 105 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Time Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Arabian Gate?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Arabian Gate handover date?
Construction of Arabian Gate is recorded as complete, with a registered completion date of October 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Arabian Gate?
Arabian Gate was 100% built at the site inspection on 1 October 2020. The site has been inspected 11 times since September 2015. The Land Department took 105 site photos at its inspections.
Is Arabian Gate delayed?
The register lists construction as complete.
Who is building Arabian Gate?
The registered developer is Time Properties. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Arabian Gate?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.