Arabian Gate construction photos
105 photos from 11 site inspections, newest first. The percentage is how much of Arabian Gate was built on the day of each visit.
1 October 2020100% built
10 June 202098% built
22 September 201993% built
13 May 201988% built
16 January 201980% built
5 September 201861% built
5 April 201846% built
26 October 201731% built
30 May 201721% built
8 December 201612% built
29 September 201512% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.