Royal Bay construction progress
The register lists Royal Bay in Palm Jumeirah as complete, with a registered completion date of January 2017. Its last site inspection on record was in October 2017. The developer is Azizi Developments.
100%
Built, at the site inspection of 2 October 2017
Construction complete
- Registered completion date
- January 2017
- Construction started
- May 2015
- First registered
- February 2016
- Developer
- Azizi Developments
- Community
- Palm Jumeirah
- Units
- 91
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- رويال باي
- Project number
- 1721
- Site inspections
- 6
Schedule
The register lists Royal Bay as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
2 October 2017
100%+1.0 pts
18 July 2017
99%+22 pts
27 April 2017
77%+16 pts
16 January 2017
61%+20 pts
29 August 2016
41%+21 pts
16 March 2016
20%
Context
Palm Jumeirah has 16 projects under construction, 45% built on average.
Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.
Own a unit in Royal Bay?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Royal Bay handover date?
- Construction of Royal Bay is recorded as complete, with a registered completion date of January 2017. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Royal Bay?
- Royal Bay was 100% built at the site inspection on 2 October 2017. The site has been inspected 6 times since March 2016. The Land Department took 55 site photos at its inspections.
- Is Royal Bay delayed?
- The register lists construction as complete.
- Who is building Royal Bay?
- The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
- Which bank holds the escrow account for Royal Bay?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi GrandAlso by Azizi Developments. 82%, Due February 2025, passed.
- Azizi Riviera ReveAlso by Azizi Developments. 77%, Due February 2025, passed.
- Azizi Venice 3Also by Azizi Developments. 76%, Due December 2025, passed.
- Azizi Venice 4Also by Azizi Developments. 62%, Due December 2025, passed.
- Palm Beach Towers -1Nearby in Palm Jumeirah. 83%, Due December 2026.
- Palm Beach Towers - 2Nearby in Palm Jumeirah. 82%, Due December 2026.
- Palm Beach Towers -3Nearby in Palm Jumeirah. 74%, Due December 2026.
- Orla By OmniyatNearby in Palm Jumeirah. 70%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.