Orla By Omniyat construction progress

The registered completion date for Orla By Omniyat in Palm Jumeirah is December 2026. At the last site inspection, in August 2026, it was 70% built. The developer is Crescent 17 Real Estate Developments.

70%

Built, at the site inspection of 21 August 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
April 2027
Construction started
January 2023
First registered
November 2022
Developer
Crescent 17 Real Estate Developments
Community
Palm Jumeirah
Units
90
Escrow bank
Mashreq Bank
Name in Arabic
أورلا من أمنيات
Project number
2455
Site inspections
12

Schedule

Between September 2025 and August 2026 the site added about 3.9 points a month. At that rate it would finish around April 2027, more than three months after its registered date of December 2026.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 August 2026

70%+10.0 pts

  • Orla By Omniyat construction site, inspection photo 1, 21 August 2026
  • Orla By Omniyat construction site, inspection photo 2, 21 August 2026
  • Orla By Omniyat construction site, inspection photo 3, 21 August 2026
  • Orla By Omniyat construction site, inspection photo 4, 21 August 2026

18 May 2026

60%+12 pts

  • Orla By Omniyat construction site, inspection photo 1, 18 May 2026
  • Orla By Omniyat construction site, inspection photo 2, 18 May 2026
  • Orla By Omniyat construction site, inspection photo 3, 18 May 2026
  • Orla By Omniyat construction site, inspection photo 4, 18 May 2026

5 February 2026

48%+22 pts

  • Orla By Omniyat construction site, inspection photo 1, 5 February 2026
  • Orla By Omniyat construction site, inspection photo 2, 5 February 2026
  • Orla By Omniyat construction site, inspection photo 3, 5 February 2026
  • Orla By Omniyat construction site, inspection photo 4, 5 February 2026

10 September 2025

26%+4.4 pts

  • Orla By Omniyat construction site, inspection photo 1, 10 September 2025
  • Orla By Omniyat construction site, inspection photo 2, 10 September 2025
  • Orla By Omniyat construction site, inspection photo 3, 10 September 2025
  • Orla By Omniyat construction site, inspection photo 4, 10 September 2025

21 May 2025

21%+6.1 pts

  • Orla By Omniyat construction site, inspection photo 1, 21 May 2025
  • Orla By Omniyat construction site, inspection photo 2, 21 May 2025
  • Orla By Omniyat construction site, inspection photo 3, 21 May 2025
  • Orla By Omniyat construction site, inspection photo 4, 21 May 2025

31 January 2025

15%+4.0 pts

  • Orla By Omniyat construction site, inspection photo 1, 31 January 2025
  • Orla By Omniyat construction site, inspection photo 2, 31 January 2025
  • Orla By Omniyat construction site, inspection photo 3, 31 January 2025
  • Orla By Omniyat construction site, inspection photo 4, 31 January 2025

8 October 2024

11%+3.3 pts

  • Orla By Omniyat construction site, inspection photo 1, 8 October 2024
  • Orla By Omniyat construction site, inspection photo 2, 8 October 2024
  • Orla By Omniyat construction site, inspection photo 3, 8 October 2024
  • Orla By Omniyat construction site, inspection photo 4, 8 October 2024

2 July 2024

8.0%+1.2 pts

  • Orla By Omniyat construction site, inspection photo 1, 2 July 2024
  • Orla By Omniyat construction site, inspection photo 2, 2 July 2024
  • Orla By Omniyat construction site, inspection photo 3, 2 July 2024

25 March 2024

6.8%+1.0 pts

  • Orla By Omniyat construction site, inspection photo 1, 25 March 2024
  • Orla By Omniyat construction site, inspection photo 2, 25 March 2024
  • Orla By Omniyat construction site, inspection photo 3, 25 March 2024

24 October 2023

5.8%+5.0 pts

  • Orla By Omniyat construction site, inspection photo 1, 24 October 2023
  • Orla By Omniyat construction site, inspection photo 2, 24 October 2023
  • Orla By Omniyat construction site, inspection photo 3, 24 October 2023
  • Orla By Omniyat construction site, inspection photo 4, 24 October 2023

All 79 site photos, by inspection date

Context

Palm Jumeirah has 16 projects under construction, 45% built on average.

Own a unit in Orla By Omniyat?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Orla By Omniyat handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Orla By Omniyat?
Orla By Omniyat was 70% built at the site inspection on 21 August 2026. The site has been inspected 12 times since September 2022. The Land Department took 79 site photos at its inspections.
Is Orla By Omniyat delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Orla By Omniyat?
The registered developer is Crescent 17 Real Estate Developments.
Which bank holds the escrow account for Orla By Omniyat?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.