Orla By Omniyat construction progress
The registered completion date for Orla By Omniyat in Palm Jumeirah is December 2026. At the last site inspection, in August 2026, it was 70% built. The developer is Crescent 17 Real Estate Developments.
70%
Built, at the site inspection of 21 August 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- April 2027
- Construction started
- January 2023
- First registered
- November 2022
- Developer
- Crescent 17 Real Estate Developments
- Community
- Palm Jumeirah
- Units
- 90
- Escrow bank
- Mashreq Bank
- Name in Arabic
- أورلا من أمنيات
- Project number
- 2455
- Site inspections
- 12
Schedule
Between September 2025 and August 2026 the site added about 3.9 points a month. At that rate it would finish around April 2027, more than three months after its registered date of December 2026.
Site inspections
21 August 2026
70%+10.0 pts
18 May 2026
60%+12 pts
5 February 2026
48%+22 pts
10 September 2025
26%+4.4 pts
21 May 2025
21%+6.1 pts
31 January 2025
15%+4.0 pts
8 October 2024
11%+3.3 pts
2 July 2024
8.0%+1.2 pts
25 March 2024
6.8%+1.0 pts
24 October 2023
5.8%+5.0 pts
Context
Palm Jumeirah has 16 projects under construction, 45% built on average.
Own a unit in Orla By Omniyat?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Orla By Omniyat handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Orla By Omniyat?
- Orla By Omniyat was 70% built at the site inspection on 21 August 2026. The site has been inspected 12 times since September 2022. The Land Department took 79 site photos at its inspections.
- Is Orla By Omniyat delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Orla By Omniyat?
- The registered developer is Crescent 17 Real Estate Developments.
- Which bank holds the escrow account for Orla By Omniyat?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Palm Beach Towers -1Nearby in Palm Jumeirah. 83%, Due December 2026.
- Palm Beach Towers - 2Nearby in Palm Jumeirah. 82%, Due December 2026.
- Palm Beach Towers -3Nearby in Palm Jumeirah. 74%, Due December 2026.
- Como ResidencesNearby in Palm Jumeirah. 25%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.











.jpeg&w=3840&q=75)



.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)



.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)