Palm Beach Towers -3 construction progress

Palm Beach Towers -3 in Palm Jumeirah is 74% built at the Land Department inspection of August 2026. Developer The Palm - Jumeirah Co. Completion registered for December 2026.

74%

Built, at the Land Department site inspection of 12 August 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
March 2028
Construction started
December 2022
Registered with the Land Department
September 2022
Community
Palm Jumeirah
Units
460
Escrow bank
Mashreq Bank
Name in Arabic
بالم بيتش تاورز - 3
Land Department project number
2449
Land Department site inspections
14

Schedule

Between October 2025 and August 2026 the site added about 1.4 points a month. At that rate it would finish around March 2028, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

12 August 2026

74%+2.8 pts

  • Palm Beach Towers -3 construction site, Land Department inspection photo 1, 12 August 2026
  • Palm Beach Towers -3 construction site, Land Department inspection photo 2, 12 August 2026
  • Palm Beach Towers -3 construction site, Land Department inspection photo 3, 12 August 2026
  • Palm Beach Towers -3 construction site, Land Department inspection photo 4, 12 August 2026

19 May 2026

71%+3.6 pts

  • Palm Beach Towers -3 construction site, Land Department inspection photo 1, 19 May 2026
  • Palm Beach Towers -3 construction site, Land Department inspection photo 2, 19 May 2026
  • Palm Beach Towers -3 construction site, Land Department inspection photo 3, 19 May 2026
  • Palm Beach Towers -3 construction site, Land Department inspection photo 4, 19 May 2026

11 February 2026

68%+6.8 pts

  • Palm Beach Towers -3 construction site, Land Department inspection photo 1, 11 February 2026
  • Palm Beach Towers -3 construction site, Land Department inspection photo 2, 11 February 2026
  • Palm Beach Towers -3 construction site, Land Department inspection photo 3, 11 February 2026
  • Palm Beach Towers -3 construction site, Land Department inspection photo 4, 11 February 2026

23 October 2025

61%+4.1 pts

  • Palm Beach Towers -3 construction site, Land Department inspection photo 1, 23 October 2025
  • Palm Beach Towers -3 construction site, Land Department inspection photo 2, 23 October 2025
  • Palm Beach Towers -3 construction site, Land Department inspection photo 3, 23 October 2025
  • Palm Beach Towers -3 construction site, Land Department inspection photo 4, 23 October 2025

30 April 2025

57%+5.6 pts

  • Palm Beach Towers -3 construction site, Land Department inspection photo 1, 30 April 2025
  • Palm Beach Towers -3 construction site, Land Department inspection photo 2, 30 April 2025
  • Palm Beach Towers -3 construction site, Land Department inspection photo 3, 30 April 2025
  • Palm Beach Towers -3 construction site, Land Department inspection photo 4, 30 April 2025

23 January 2025

51%+9.6 pts

  • Palm Beach Towers -3 construction site, Land Department inspection photo 1, 23 January 2025
  • Palm Beach Towers -3 construction site, Land Department inspection photo 2, 23 January 2025
  • Palm Beach Towers -3 construction site, Land Department inspection photo 3, 23 January 2025
  • Palm Beach Towers -3 construction site, Land Department inspection photo 4, 23 January 2025

25 September 2024

42%+6.8 pts

  • Palm Beach Towers -3 construction site, Land Department inspection photo 1, 25 September 2024
  • Palm Beach Towers -3 construction site, Land Department inspection photo 2, 25 September 2024
  • Palm Beach Towers -3 construction site, Land Department inspection photo 3, 25 September 2024
  • Palm Beach Towers -3 construction site, Land Department inspection photo 4, 25 September 2024

28 May 2024

35%+2.3 pts

  • Palm Beach Towers -3 construction site, Land Department inspection photo 1, 28 May 2024
  • Palm Beach Towers -3 construction site, Land Department inspection photo 2, 28 May 2024
  • Palm Beach Towers -3 construction site, Land Department inspection photo 3, 28 May 2024
  • Palm Beach Towers -3 construction site, Land Department inspection photo 4, 28 May 2024

25 January 2024

33%+1.5 pts

  • Palm Beach Towers -3 construction site, Land Department inspection photo 1, 25 January 2024
  • Palm Beach Towers -3 construction site, Land Department inspection photo 2, 25 January 2024
  • Palm Beach Towers -3 construction site, Land Department inspection photo 3, 25 January 2024

22 November 2023

31%+1.1 pts

  • Palm Beach Towers -3 construction site, Land Department inspection photo 1, 22 November 2023
  • Palm Beach Towers -3 construction site, Land Department inspection photo 2, 22 November 2023
  • Palm Beach Towers -3 construction site, Land Department inspection photo 3, 22 November 2023
  • Palm Beach Towers -3 construction site, Land Department inspection photo 4, 22 November 2023

All 104 site photos, by inspection date

Context

Palm Jumeirah has 18 projects under construction, 48% built on average.

The Palm - Jumeirah Co has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Palm Beach Towers -3?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Palm Beach Towers -3 be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around March 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Palm Beach Towers -3 is built?
74%, measured at the Land Department site inspection on 12 August 2026. The Land Department engineers have inspected the site 14 times since September 2022.
Is Palm Beach Towers -3 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building Palm Beach Towers -3?
The registered developer is The Palm - Jumeirah Co. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Palm Beach Towers -3?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.