Palm Beach Towers - 2 construction progress
Palm Beach Towers - 2 in Palm Jumeirah is 82% built at the Land Department inspection of August 2026. Developer The Palm - Jumeirah Co. Completion registered for December 2026.
82%
Built, at the Land Department site inspection of 12 August 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- October 2027
- Construction started
- December 2022
- Registered with the Land Department
- July 2022
- Developer
- The Palm - Jumeirah Co
- Community
- Palm Jumeirah
- Units
- 321
- Escrow bank
- Mashreq Bank
- Name in Arabic
- مشروع بالم بيتش تاورز - 2
- Land Department project number
- 2429
- Land Department site inspections
- 14
Schedule
Between October 2025 and August 2026 the site added about 1.3 points a month. At that rate it would finish around October 2027, more than three months after the December 2026 date registered with the Land Department.
Site inspections
12 August 2026
82%+2.0 pts
21 May 2026
80%+2.4 pts
11 February 2026
77%+8.1 pts
23 October 2025
69%+5.0 pts
30 April 2025
64%+5.8 pts
23 January 2025
58%+11 pts
25 September 2024
48%+10.0 pts
28 May 2024
38%+1.3 pts
25 January 2024
36%+2.5 pts
22 November 2023
34%+1.1 pts
Context
Palm Jumeirah has 18 projects under construction, 48% built on average.
The Palm - Jumeirah Co has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Palm Beach Towers - 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Palm Beach Towers - 2 be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Palm Beach Towers - 2 is built?
- 82%, measured at the Land Department site inspection on 12 August 2026. The Land Department engineers have inspected the site 14 times since June 2022.
- Is Palm Beach Towers - 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building Palm Beach Towers - 2?
- The registered developer is The Palm - Jumeirah Co. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Palm Beach Towers - 2?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Palm Beach Towers -1Also by The Palm - Jumeirah Co. 83%, Due December 2026.
- Palm Beach Towers -3Also by The Palm - Jumeirah Co. 74%, Due December 2026.
- Como ResidencesAlso by The Palm - Jumeirah Co. 21%, Due March 2027.
- Ava At Palm Jumeirah By OmniyatNearby in Palm Jumeirah. 96%, Due June 2026, passed.
- Orla By OmniyatNearby in Palm Jumeirah. 70%.
- One CrescentNearby in Palm Jumeirah. 80%.
- LuceNearby in Palm Jumeirah. 98%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)