Luce construction progress

The register lists Luce in Palm Jumeirah as complete, with a registered completion date of December 2025. Its last site inspection on record was in August 2026. The developer is Taraf Development.

100%

Built, at the site inspection of 31 August 2026

Construction complete

Registered completion date
December 2025
Construction started
July 2023
First registered
February 2023
Community
Palm Jumeirah
Units
38
Escrow bank
First Abu Dhabi Bank
Name in Arabic
لوتشه
Project number
2572
Site inspections
12

Schedule

The register lists Luce as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

31 August 2026

98%+6.9 pts

  • Luce construction site, inspection photo 1, 31 August 2026
  • Luce construction site, inspection photo 2, 31 August 2026
  • Luce construction site, inspection photo 3, 31 August 2026
  • Luce construction site, inspection photo 4, 31 August 2026

11 May 2026

91%+9.2 pts

  • Luce construction site, inspection photo 1, 11 May 2026
  • Luce construction site, inspection photo 2, 11 May 2026
  • Luce construction site, inspection photo 3, 11 May 2026
  • Luce construction site, inspection photo 4, 11 May 2026

26 January 2026

82%+18 pts

  • Luce construction site, inspection photo 1, 26 January 2026
  • Luce construction site, inspection photo 2, 26 January 2026
  • Luce construction site, inspection photo 3, 26 January 2026
  • Luce construction site, inspection photo 4, 26 January 2026

1 October 2025

64%+16 pts

  • Luce construction site, inspection photo 1, 1 October 2025
  • Luce construction site, inspection photo 2, 1 October 2025
  • Luce construction site, inspection photo 3, 1 October 2025
  • Luce construction site, inspection photo 4, 1 October 2025

19 June 2025

48%+9.8 pts

  • Luce construction site, inspection photo 1, 19 June 2025
  • Luce construction site, inspection photo 2, 19 June 2025
  • Luce construction site, inspection photo 3, 19 June 2025
  • Luce construction site, inspection photo 4, 19 June 2025

18 April 2025

38%+15 pts

  • Luce construction site, inspection photo 1, 18 April 2025
  • Luce construction site, inspection photo 2, 18 April 2025
  • Luce construction site, inspection photo 3, 18 April 2025
  • Luce construction site, inspection photo 4, 18 April 2025

22 January 2025

23%+7.9 pts

  • Luce construction site, inspection photo 1, 22 January 2025
  • Luce construction site, inspection photo 2, 22 January 2025
  • Luce construction site, inspection photo 3, 22 January 2025
  • Luce construction site, inspection photo 4, 22 January 2025

8 October 2024

15%+6.0 pts

  • Luce construction site, inspection photo 1, 8 October 2024
  • Luce construction site, inspection photo 2, 8 October 2024
  • Luce construction site, inspection photo 3, 8 October 2024
  • Luce construction site, inspection photo 4, 8 October 2024

25 August 2024

9.0%+3.6 pts

  • Luce construction site, inspection photo 1, 25 August 2024
  • Luce construction site, inspection photo 2, 25 August 2024
  • Luce construction site, inspection photo 3, 25 August 2024
  • Luce construction site, inspection photo 4, 25 August 2024

3 April 2024

5.5%+5.5 pts

  • Luce construction site, inspection photo 1, 3 April 2024
  • Luce construction site, inspection photo 2, 3 April 2024

All 70 site photos, by inspection date

Context

Palm Jumeirah has 16 projects under construction, 45% built on average.

Taraf Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Luce?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Luce handover date?
Construction of Luce is recorded as complete, with a registered completion date of December 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Luce?
Luce was 100% built at the site inspection on 31 August 2026. The site has been inspected 12 times since February 2023. The Land Department took 70 site photos at its inspections.
Is Luce delayed?
The register lists construction as complete.
Who is building Luce?
The registered developer is Taraf Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Luce?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.