Luce construction photos

70 photos from 12 site inspections, newest first. The percentage is how much of Luce was built on the day of each visit.

31 August 202698% built

11 May 202691% built

26 January 202682% built

1 October 202564% built

19 June 202548% built

18 April 202538% built

22 January 202523% built

8 October 202415% built

25 August 20249.0% built

3 April 20245.5% built

21 June 20230% built

6 February 20230% built

Back to Luce construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.