Terra Golf Collection construction progress
The registered completion date for Terra Golf Collection in Jumeirah Golf Estates is December 2027. At the last site inspection, in September 2026, it was 20% built. The developer is Taraf Development.
20%
Built, at the site inspection of 1 September 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- May 2031
- Construction started
- March 2024
- First registered
- December 2023
- Developer
- Taraf Development
- Community
- Jumeirah Golf Estates
- Units
- 66
- Escrow bank
- Emirates NBD
- Name in Arabic
- تيرا غولف كوليكشن
- Project number
- 2877
- Site inspections
- 9
Schedule
Between September 2025 and September 2026 the site added about 1.4 points a month. At that rate it would finish around May 2031, more than three months after its registered date of December 2027.
Site inspections
1 September 2026
20%+7.1 pts
14 May 2026
13%+6.3 pts
29 January 2026
6.6%+3.2 pts
9 September 2025
3.4%
7 August 2025
3.4%+1.1 pts
10 April 2025
2.3%+2.2 pts
16 December 2024
0.1%+0.1 pts
3 July 2024
0.1%+0.1 pts
5 December 2023
0%
Context
Jumeirah Golf Estates has 4 projects under construction, 49% built on average.
Taraf Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Terra Golf Collection?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Terra Golf Collection handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Terra Golf Collection?
- Terra Golf Collection was 20% built at the site inspection on 1 September 2026. The site has been inspected 9 times since December 2023. The Land Department took 59 site photos at its inspections.
- Is Terra Golf Collection delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Terra Golf Collection?
- The registered developer is Taraf Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Terra Golf Collection?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Terrazzo ResidencesAlso by Taraf Development. 95%, Due May 2026, passed.
- Cello ResidencesAlso by Taraf Development. 39%.
- Karl Lagerfeld Villas By TarafAlso by Taraf Development. 11%.
- Jouri HillsNearby in Jumeirah Golf Estates. 78%, Due June 2026, passed.
- Signature MansionsNearby in Jumeirah Golf Estates. 87%, Due May 2026, passed.
- D VillasNearby in Jumeirah Golf Estates. 9.1%, Due December 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)














.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)