Cello Residences construction progress

Cello Residences in Jumeirah Village Circle is 39% built at the Land Department inspection of September 2026. Developer Taraf Development.

39%

Built, at the Land Department site inspection of 4 September 2026

Finish at recent pace
December 2028
Construction started
February 2024
Registered with the Land Department
January 2024
Units
392
Escrow bank
Emirates NBD
Name in Arabic
تشيللو ريزيدنسز
Land Department project number
2843
Land Department site inspections
9

Schedule

Since October 2025 Cello Residences has added about 2.3 points a month. At that rate the site reaches 100% around December 2028. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

4 September 2026

39%+12 pts

  • Cello Residences construction site, Land Department inspection photo 1, 4 September 2026
  • Cello Residences construction site, Land Department inspection photo 2, 4 September 2026
  • Cello Residences construction site, Land Department inspection photo 3, 4 September 2026
  • Cello Residences construction site, Land Department inspection photo 4, 4 September 2026

21 May 2026

27%+6.5 pts

  • Cello Residences construction site, Land Department inspection photo 1, 21 May 2026
  • Cello Residences construction site, Land Department inspection photo 2, 21 May 2026
  • Cello Residences construction site, Land Department inspection photo 3, 21 May 2026
  • Cello Residences construction site, Land Department inspection photo 4, 21 May 2026

17 February 2026

20%+4.2 pts

  • Cello Residences construction site, Land Department inspection photo 1, 17 February 2026
  • Cello Residences construction site, Land Department inspection photo 2, 17 February 2026
  • Cello Residences construction site, Land Department inspection photo 3, 17 February 2026
  • Cello Residences construction site, Land Department inspection photo 4, 17 February 2026

29 October 2025

16%+7.0 pts

  • Cello Residences construction site, Land Department inspection photo 1, 29 October 2025
  • Cello Residences construction site, Land Department inspection photo 2, 29 October 2025
  • Cello Residences construction site, Land Department inspection photo 3, 29 October 2025
  • Cello Residences construction site, Land Department inspection photo 4, 29 October 2025

15 July 2025

8.9%+1.2 pts

  • Cello Residences construction site, Land Department inspection photo 1, 15 July 2025
  • Cello Residences construction site, Land Department inspection photo 2, 15 July 2025
  • Cello Residences construction site, Land Department inspection photo 3, 15 July 2025
  • Cello Residences construction site, Land Department inspection photo 4, 15 July 2025

19 February 2025

7.7%+5.0 pts

  • Cello Residences construction site, Land Department inspection photo 1, 19 February 2025
  • Cello Residences construction site, Land Department inspection photo 2, 19 February 2025
  • Cello Residences construction site, Land Department inspection photo 3, 19 February 2025
  • Cello Residences construction site, Land Department inspection photo 4, 19 February 2025

4 November 2024

2.7%+2.7 pts

  • Cello Residences construction site, Land Department inspection photo 1, 4 November 2024
  • Cello Residences construction site, Land Department inspection photo 2, 4 November 2024
  • Cello Residences construction site, Land Department inspection photo 3, 4 November 2024

3 July 2024

0%+0.0 pts

  • Cello Residences construction site, Land Department inspection photo 1, 3 July 2024
  • Cello Residences construction site, Land Department inspection photo 2, 3 July 2024

8 November 2023

0%

  • Cello Residences construction site, Land Department inspection photo 1, 8 November 2023
  • Cello Residences construction site, Land Department inspection photo 2, 8 November 2023

All 43 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Taraf Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Cello Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Cello Residences be completed?
The Land Department has no completion date on record for Cello Residences yet.
How much of Cello Residences is built?
39%, measured at the Land Department site inspection on 4 September 2026. The Land Department engineers have inspected the site 9 times since November 2023.
Who is building Cello Residences?
The registered developer is Taraf Development. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Cello Residences?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.