Cello Residences construction progress
Cello Residences in Jumeirah Village Circle is 39% built at the Land Department inspection of September 2026. Developer Taraf Development.
39%
Built, at the Land Department site inspection of 4 September 2026
- Finish at recent pace
- December 2028
- Construction started
- February 2024
- Registered with the Land Department
- January 2024
- Developer
- Taraf Development
- Community
- Jumeirah Village Circle
- Units
- 392
- Escrow bank
- Emirates NBD
- Name in Arabic
- تشيللو ريزيدنسز
- Land Department project number
- 2843
- Land Department site inspections
- 9
Schedule
Since October 2025 Cello Residences has added about 2.3 points a month. At that rate the site reaches 100% around December 2028. The Land Department has no completion date on record to compare it with.
Site inspections
4 September 2026
39%+12 pts
21 May 2026
27%+6.5 pts
17 February 2026
20%+4.2 pts
29 October 2025
16%+7.0 pts
15 July 2025
8.9%+1.2 pts
19 February 2025
7.7%+5.0 pts
4 November 2024
2.7%+2.7 pts
3 July 2024
0%+0.0 pts
8 November 2023
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Taraf Development has 5 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Cello Residences?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Cello Residences be completed?
- The Land Department has no completion date on record for Cello Residences yet.
- How much of Cello Residences is built?
- 39%, measured at the Land Department site inspection on 4 September 2026. The Land Department engineers have inspected the site 9 times since November 2023.
- Who is building Cello Residences?
- The registered developer is Taraf Development. It has 4 other projects under construction in Dubai.
- Which bank holds the escrow account for Cello Residences?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- LuceAlso by Taraf Development. 98%.
- Terrazzo ResidencesAlso by Taraf Development. 95%, Due May 2026, passed.
- Terra Golf CollectionAlso by Taraf Development. 20%, Due December 2027.
- Karl Lagerfeld Villas By TarafAlso by Taraf Development. 11%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)