Cello Residences construction progress
No completion date is registered for Cello Residences in Jumeirah Village Circle yet. At the last site inspection, in September 2026, it was 39% built. The developer is Taraf Development.
39%
Built, at the site inspection of 4 September 2026
- Finish at recent pace
- December 2028
- Construction started
- February 2024
- First registered
- January 2024
- Developer
- Taraf Development
- Community
- Jumeirah Village Circle
- Units
- 392
- Escrow bank
- Emirates NBD
- Name in Arabic
- تشيللو ريزيدنسز
- Project number
- 2843
- Site inspections
- 9
Schedule
Since October 2025 Cello Residences has added about 2.3 points a month. At that rate the site reaches 100% around December 2028. No completion date is on record to compare it with.
Site inspections
4 September 2026
39%+12 pts
21 May 2026
27%+6.5 pts
17 February 2026
20%+4.2 pts
29 October 2025
16%+7.0 pts
15 July 2025
8.9%+1.2 pts
19 February 2025
7.7%+5.0 pts
4 November 2024
2.7%+2.7 pts
3 July 2024
0%+0.0 pts
8 November 2023
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Taraf Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Cello Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Cello Residences handover date?
- No completion date is on record for Cello Residences yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Cello Residences?
- Cello Residences was 39% built at the site inspection on 4 September 2026. The site has been inspected 9 times since November 2023. The Land Department took 43 site photos at its inspections.
- Who is building Cello Residences?
- The registered developer is Taraf Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Cello Residences?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Terrazzo ResidencesAlso by Taraf Development. 95%, Due May 2026, passed.
- Terra Golf CollectionAlso by Taraf Development. 20%, Due December 2027.
- Karl Lagerfeld Villas By TarafAlso by Taraf Development. 11%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.