Cello Residences construction progress

No completion date is registered for Cello Residences in Jumeirah Village Circle yet. At the last site inspection, in September 2026, it was 39% built. The developer is Taraf Development.

39%

Built, at the site inspection of 4 September 2026

Finish at recent pace
December 2028
Construction started
February 2024
First registered
January 2024
Units
392
Escrow bank
Emirates NBD
Name in Arabic
تشيللو ريزيدنسز
Project number
2843
Site inspections
9

Schedule

Since October 2025 Cello Residences has added about 2.3 points a month. At that rate the site reaches 100% around December 2028. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

4 September 2026

39%+12 pts

  • Cello Residences construction site, inspection photo 1, 4 September 2026
  • Cello Residences construction site, inspection photo 2, 4 September 2026
  • Cello Residences construction site, inspection photo 3, 4 September 2026
  • Cello Residences construction site, inspection photo 4, 4 September 2026

21 May 2026

27%+6.5 pts

  • Cello Residences construction site, inspection photo 1, 21 May 2026
  • Cello Residences construction site, inspection photo 2, 21 May 2026
  • Cello Residences construction site, inspection photo 3, 21 May 2026
  • Cello Residences construction site, inspection photo 4, 21 May 2026

17 February 2026

20%+4.2 pts

  • Cello Residences construction site, inspection photo 1, 17 February 2026
  • Cello Residences construction site, inspection photo 2, 17 February 2026
  • Cello Residences construction site, inspection photo 3, 17 February 2026
  • Cello Residences construction site, inspection photo 4, 17 February 2026

29 October 2025

16%+7.0 pts

  • Cello Residences construction site, inspection photo 1, 29 October 2025
  • Cello Residences construction site, inspection photo 2, 29 October 2025
  • Cello Residences construction site, inspection photo 3, 29 October 2025
  • Cello Residences construction site, inspection photo 4, 29 October 2025

15 July 2025

8.9%+1.2 pts

  • Cello Residences construction site, inspection photo 1, 15 July 2025
  • Cello Residences construction site, inspection photo 2, 15 July 2025
  • Cello Residences construction site, inspection photo 3, 15 July 2025
  • Cello Residences construction site, inspection photo 4, 15 July 2025

19 February 2025

7.7%+5.0 pts

  • Cello Residences construction site, inspection photo 1, 19 February 2025
  • Cello Residences construction site, inspection photo 2, 19 February 2025
  • Cello Residences construction site, inspection photo 3, 19 February 2025
  • Cello Residences construction site, inspection photo 4, 19 February 2025

4 November 2024

2.7%+2.7 pts

  • Cello Residences construction site, inspection photo 1, 4 November 2024
  • Cello Residences construction site, inspection photo 2, 4 November 2024
  • Cello Residences construction site, inspection photo 3, 4 November 2024

3 July 2024

0%+0.0 pts

  • Cello Residences construction site, inspection photo 1, 3 July 2024
  • Cello Residences construction site, inspection photo 2, 3 July 2024

8 November 2023

0%

  • Cello Residences construction site, inspection photo 1, 8 November 2023
  • Cello Residences construction site, inspection photo 2, 8 November 2023

All 43 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Taraf Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Cello Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cello Residences handover date?
No completion date is on record for Cello Residences yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Cello Residences?
Cello Residences was 39% built at the site inspection on 4 September 2026. The site has been inspected 9 times since November 2023. The Land Department took 43 site photos at its inspections.
Who is building Cello Residences?
The registered developer is Taraf Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Cello Residences?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.