Terrazzo Residences construction progress

Terrazzo Residences in Jumeirah Village Circle was registered to complete in May 2026 and is still under construction. At the last site inspection, in July 2026, it was 95% built. The developer is Taraf Development.

95%

Built, at the site inspection of 27 July 2026

6 months past its registered completion date

Registered completion date
May 2026
Finish at recent pace
September 2026
Construction started
November 2023
First registered
July 2023
Units
211
Escrow bank
Emirates NBD
Name in Arabic
تيرازو ريزيدنسز
Project number
2675
Site inspections
10

Schedule

Terrazzo Residences was registered to complete in May 2026, 6 months ago, and is still under construction. Over the last year of inspections it has added about 3.6 points a month. Kept at that rate, the site would reach 100% around September 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 July 2026

95%+11 pts

  • Terrazzo Residences construction site, inspection photo 1, 27 July 2026
  • Terrazzo Residences construction site, inspection photo 2, 27 July 2026
  • Terrazzo Residences construction site, inspection photo 3, 27 July 2026
  • Terrazzo Residences construction site, inspection photo 4, 27 July 2026

6 April 2026

84%+16 pts

  • Terrazzo Residences construction site, inspection photo 1, 6 April 2026
  • Terrazzo Residences construction site, inspection photo 2, 6 April 2026
  • Terrazzo Residences construction site, inspection photo 3, 6 April 2026
  • Terrazzo Residences construction site, inspection photo 4, 6 April 2026

3 December 2025

68%+9.1 pts

  • Terrazzo Residences construction site, inspection photo 1, 3 December 2025
  • Terrazzo Residences construction site, inspection photo 2, 3 December 2025
  • Terrazzo Residences construction site, inspection photo 3, 3 December 2025
  • Terrazzo Residences construction site, inspection photo 4, 3 December 2025

24 September 2025

59%+20 pts

  • Terrazzo Residences construction site, inspection photo 1, 24 September 2025
  • Terrazzo Residences construction site, inspection photo 2, 24 September 2025
  • Terrazzo Residences construction site, inspection photo 3, 24 September 2025
  • Terrazzo Residences construction site, inspection photo 4, 24 September 2025

17 June 2025

39%+19 pts

  • Terrazzo Residences construction site, inspection photo 1, 17 June 2025
  • Terrazzo Residences construction site, inspection photo 2, 17 June 2025
  • Terrazzo Residences construction site, inspection photo 3, 17 June 2025
  • Terrazzo Residences construction site, inspection photo 4, 17 June 2025

12 March 2025

20%+13 pts

  • Terrazzo Residences construction site, inspection photo 1, 12 March 2025
  • Terrazzo Residences construction site, inspection photo 2, 12 March 2025
  • Terrazzo Residences construction site, inspection photo 3, 12 March 2025
  • Terrazzo Residences construction site, inspection photo 4, 12 March 2025

4 November 2024

6.8%+6.7 pts

  • Terrazzo Residences construction site, inspection photo 1, 4 November 2024
  • Terrazzo Residences construction site, inspection photo 2, 4 November 2024
  • Terrazzo Residences construction site, inspection photo 3, 4 November 2024
  • Terrazzo Residences construction site, inspection photo 4, 4 November 2024

3 July 2024

0%

  • Terrazzo Residences construction site, inspection photo 1, 3 July 2024
  • Terrazzo Residences construction site, inspection photo 2, 3 July 2024

13 December 2023

0%+0.0 pts

  • Terrazzo Residences construction site, inspection photo 1, 13 December 2023
  • Terrazzo Residences construction site, inspection photo 2, 13 December 2023
  • Terrazzo Residences construction site, inspection photo 3, 13 December 2023

24 May 2023

0%

  • Terrazzo Residences construction site, inspection photo 1, 24 May 2023

All 72 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Taraf Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Terrazzo Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Terrazzo Residences handover date?
The registered completion date was May 2026, and the register still lists Terrazzo Residences as under construction. At the pace of its recent inspections the site would reach 100% around September 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Terrazzo Residences?
Terrazzo Residences was 95% built at the site inspection on 27 July 2026. The site has been inspected 10 times since May 2023. The Land Department took 72 site photos at its inspections.
Is Terrazzo Residences delayed?
Yes. Its registered completion date of May 2026 has passed and the project is still listed as under construction.
Who is building Terrazzo Residences?
The registered developer is Taraf Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Terrazzo Residences?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.