Ocean Pearl 2 By Sd construction progress
Ocean Pearl 2 By Sd in Palm Deira is 23% built at the Land Department inspection of September 2026. Developer Samana Star Real Estate Development. Completion registered for March 2027.
23%
Built, at the Land Department site inspection of 17 September 2026
Running behind its date
- Completion date (Land Department)
- March 2027
- Finish at recent pace
- February 2030
- Construction started
- January 2024
- Registered with the Land Department
- November 2024
- Developer
- Samana Star Real Estate Development
- Community
- Palm Deira
- Units
- 96
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- أوشن برل 2 باي اس دي
- Land Department project number
- 3238
- Land Department site inspections
- 6
Schedule
Between December 2025 and September 2026 the site added about 1.9 points a month. At that rate it would finish around February 2030, more than three months after the March 2027 date registered with the Land Department.
Site inspections
17 September 2026
23%+15 pts
21 April 2026
8.1%+2.3 pts
4 December 2025
5.8%+4.4 pts
26 August 2025
1.4%+0.2 pts
8 April 2025
1.2%+1.2 pts
7 October 2024
0%
Context
Palm Deira has 95 projects under construction, 22% built on average.
Samana Star Real Estate Development has 8 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Ocean Pearl 2 By Sd?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Ocean Pearl 2 By Sd be completed?
- The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around February 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Ocean Pearl 2 By Sd is built?
- 23%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 6 times since October 2024.
- Is Ocean Pearl 2 By Sd delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Ocean Pearl 2 By Sd?
- The registered developer is Samana Star Real Estate Development. It has 7 other projects under construction in Dubai.
- Which bank holds the escrow account for Ocean Pearl 2 By Sd?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Manhattan 1 By SdAlso by Samana Star Real Estate Development. 30%.
- Manhattan 2 By SdAlso by Samana Star Real Estate Development. 21%, Due November 2026.
- California 2 By SdAlso by Samana Star Real Estate Development. 34%.
- Ocean Pearl By SdAlso by Samana Star Real Estate Development. 25%, Due December 2026.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.