Ocean Pearl 2 By Sd construction progress
The registered completion date for Ocean Pearl 2 By Sd in Palm Deira is March 2027. At the last site inspection, in September 2026, it was 23% built. The developer is Samana Star Real Estate Development.
23%
Built, at the site inspection of 17 September 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- February 2030
- Construction started
- January 2024
- First registered
- November 2024
- Developer
- Samana Star Real Estate Development
- Community
- Palm Deira
- Units
- 96
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- أوشن برل 2 باي اس دي
- Project number
- 3238
- Site inspections
- 6
Schedule
Between December 2025 and September 2026 the site added about 1.9 points a month. At that rate it would finish around February 2030, more than three months after its registered date of March 2027.
Site inspections
17 September 2026
23%+15 pts
21 April 2026
8.1%+2.3 pts
4 December 2025
5.8%+4.4 pts
26 August 2025
1.4%+0.2 pts
8 April 2025
1.2%+1.2 pts
7 October 2024
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Samana Star Real Estate Development has 8 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Ocean Pearl 2 By Sd?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Ocean Pearl 2 By Sd handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Ocean Pearl 2 By Sd?
- Ocean Pearl 2 By Sd was 23% built at the site inspection on 17 September 2026. The site has been inspected 6 times since October 2024. The Land Department took 26 site photos at its inspections.
- Is Ocean Pearl 2 By Sd delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Ocean Pearl 2 By Sd?
- The registered developer is Samana Star Real Estate Development. It has 7 other projects under construction in Dubai.
- Which bank holds the escrow account for Ocean Pearl 2 By Sd?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Manhattan 1 By SdAlso by Samana Star Real Estate Development. 30%.
- Manhattan 2 By SdAlso by Samana Star Real Estate Development. 21%, Due November 2026, passed.
- California 2 By SdAlso by Samana Star Real Estate Development. 34%, Due October 2026, passed.
- Ocean Pearl By SdAlso by Samana Star Real Estate Development. 25%, Due December 2026.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)











.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)