Beach Walk Residences 4 By Imtiaz construction progress

Beach Walk Residences 4 By Imtiaz in Palm Deira is 43% built at the Land Department inspection of August 2026. Developer Imtiaz Real Estate Investment & Development. Completion registered for April 2027.

43%

Built, at the Land Department site inspection of 13 August 2026

Running behind its date

Completion date (Land Department)
April 2027
Finish at recent pace
October 2027
Construction started
April 2025
Registered with the Land Department
May 2025
Community
Palm Deira
Units
70
Escrow bank
First Abu Dhabi Bank
Name in Arabic
بيتش ووك ريزيدنسز 4 من امتياز
Land Department project number
3707
Land Department site inspections
6

Schedule

Between October 2025 and August 2026 the site added about 3.9 points a month. At that rate it would finish around October 2027, more than three months after the April 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 August 2026

43%+8.7 pts

  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 1, 13 August 2026
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 2, 13 August 2026
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 3, 13 August 2026
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 4, 13 August 2026

1 June 2026

34%+17 pts

  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 1, 1 June 2026
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 2, 1 June 2026
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 3, 1 June 2026
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 4, 1 June 2026

26 February 2026

17%+12 pts

  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 1, 26 February 2026
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 2, 26 February 2026
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 3, 26 February 2026
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 4, 26 February 2026

22 October 2025

4.6%+0.9 pts

  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 1, 22 October 2025
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 2, 22 October 2025
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 3, 22 October 2025
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 4, 22 October 2025

18 July 2025

3.7%+3.7 pts

  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 1, 18 July 2025
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 2, 18 July 2025
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 3, 18 July 2025

21 April 2025

0%

  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 1, 21 April 2025
  • Beach Walk Residences 4 By Imtiaz construction site, Land Department inspection photo 2, 21 April 2025

All 36 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Imtiaz Real Estate Investment & Development has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Beach Walk Residences 4 By Imtiaz?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Beach Walk Residences 4 By Imtiaz be completed?
The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Beach Walk Residences 4 By Imtiaz is built?
43%, measured at the Land Department site inspection on 13 August 2026. The Land Department engineers have inspected the site 6 times since April 2025.
Is Beach Walk Residences 4 By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Beach Walk Residences 4 By Imtiaz?
The registered developer is Imtiaz Real Estate Investment & Development. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Beach Walk Residences 4 By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.