The Watercrest By Ellington construction progress
The Watercrest By Ellington in Mohammed Bin Rashid Al Maktoum District 11 is 2.2% built at the Land Department inspection of July 2026. Developer Ellington Properties Development. Completion registered for March 2028.
2.2%
Built, at the Land Department site inspection of 24 July 2026
Running behind its date
- Completion date (Land Department)
- March 2028
- Finish at recent pace
- June 2079
- Construction started
- January 2025
- Registered with the Land Department
- March 2025
- Developer
- Ellington Properties Development
- Units
- 84
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- ذا واتركريست من إلينغتون
- Land Department project number
- 3444
- Land Department site inspections
- 3
Schedule
Between February 2026 and July 2026 the site added about 0.2 points a month. At that rate it would finish around June 2079, more than three months after the March 2028 date registered with the Land Department.
Site inspections
24 July 2026
2.2%+0.8 pts
16 February 2026
1.4%+1.4 pts
22 January 2025
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 26% built on average.
Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.
Own a unit in The Watercrest By Ellington?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Watercrest By Ellington be completed?
- The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around June 2079. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Watercrest By Ellington is built?
- 2.2%, measured at the Land Department site inspection on 24 July 2026. The Land Department engineers have inspected the site 3 times since January 2025.
- Is The Watercrest By Ellington delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building The Watercrest By Ellington?
- The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
- Which bank holds the escrow account for The Watercrest By Ellington?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- The PortmanAlso by Ellington Properties Development. 79%, Due September 2025, passed.
- The HighburyAlso by Ellington Properties Development. 80%.
- Uh West By EllingtonAlso by Ellington Properties Development. 71%, Due March 2026, passed.
- Uh East By EllingtonAlso by Ellington Properties Development. 47%, Due March 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%.
- Wadi Villas By AristaNearby in Mohammed Bin Rashid Al Maktoum District 11. 60%.
- Lua ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 64%, Due March 2026, passed.
- Nineteen Riviera LagoonNearby in Mohammed Bin Rashid Al Maktoum District 11. 34%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpg&w=3840&q=75)