The Beachfront Villas By Ellington construction progress

The Beachfront Villas By Ellington in Mohammed Bin Rashid Al Maktoum District 11 was registered to complete in August 2026 and is still under construction. At the last site inspection, in October 2026, it was 47% built. The developer is Ellington Properties Development.

47%

Built, at the site inspection of 26 October 2026

3 months past its registered completion date

Registered completion date
August 2026
Finish at recent pace
February 2028
Construction started
December 2023
First registered
January 2024
Units
21
Escrow bank
Commercial Bank of Dubai
Name in Arabic
ذا بيتش فرونت فيلاز من إلينغتون
Project number
2894
Site inspections
7

Schedule

The Beachfront Villas By Ellington was registered to complete in August 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 3.4 points a month. Kept at that rate, the site would reach 100% around February 2028.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 October 2026

47%+12 pts

  • The Beachfront Villas By Ellington construction site, inspection photo 1, 26 October 2026
  • The Beachfront Villas By Ellington construction site, inspection photo 2, 26 October 2026
  • The Beachfront Villas By Ellington construction site, inspection photo 3, 26 October 2026
  • The Beachfront Villas By Ellington construction site, inspection photo 4, 26 October 2026

9 June 2026

35%+18 pts

  • The Beachfront Villas By Ellington construction site, inspection photo 1, 9 June 2026
  • The Beachfront Villas By Ellington construction site, inspection photo 2, 9 June 2026
  • The Beachfront Villas By Ellington construction site, inspection photo 3, 9 June 2026
  • The Beachfront Villas By Ellington construction site, inspection photo 4, 9 June 2026

2 February 2026

18%+6.7 pts

  • The Beachfront Villas By Ellington construction site, inspection photo 1, 2 February 2026
  • The Beachfront Villas By Ellington construction site, inspection photo 2, 2 February 2026
  • The Beachfront Villas By Ellington construction site, inspection photo 3, 2 February 2026
  • The Beachfront Villas By Ellington construction site, inspection photo 4, 2 February 2026

14 October 2025

11%+7.8 pts

  • The Beachfront Villas By Ellington construction site, inspection photo 1, 14 October 2025
  • The Beachfront Villas By Ellington construction site, inspection photo 2, 14 October 2025
  • The Beachfront Villas By Ellington construction site, inspection photo 3, 14 October 2025
  • The Beachfront Villas By Ellington construction site, inspection photo 4, 14 October 2025

4 June 2025

3.1%+3.1 pts

  • The Beachfront Villas By Ellington construction site, inspection photo 1, 4 June 2025
  • The Beachfront Villas By Ellington construction site, inspection photo 2, 4 June 2025
  • The Beachfront Villas By Ellington construction site, inspection photo 3, 4 June 2025
  • The Beachfront Villas By Ellington construction site, inspection photo 4, 4 June 2025

2 July 2024

0.1%+0.1 pts

  • The Beachfront Villas By Ellington construction site, inspection photo 1, 2 July 2024
  • The Beachfront Villas By Ellington construction site, inspection photo 2, 2 July 2024

21 December 2023

0%

  • The Beachfront Villas By Ellington construction site, inspection photo 1, 21 December 2023
  • The Beachfront Villas By Ellington construction site, inspection photo 2, 21 December 2023

All 43 site photos, by inspection date

Context

Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.

Ellington Properties Development has 18 projects under construction in Dubai; 6 have passed their registered completion date.

Own a unit in The Beachfront Villas By Ellington?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Beachfront Villas By Ellington handover date?
The registered completion date was August 2026, and the register still lists The Beachfront Villas By Ellington as under construction. At the pace of its recent inspections the site would reach 100% around February 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Beachfront Villas By Ellington?
The Beachfront Villas By Ellington was 47% built at the site inspection on 26 October 2026. The site has been inspected 7 times since December 2023. The Land Department took 43 site photos at its inspections.
Is The Beachfront Villas By Ellington delayed?
Yes. Its registered completion date of August 2026 has passed and the project is still listed as under construction.
Who is building The Beachfront Villas By Ellington?
The registered developer is Ellington Properties Development. It has 17 other projects under construction in Dubai.
Which bank holds the escrow account for The Beachfront Villas By Ellington?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.