Rome 3 By Sd construction progress
The registered completion date for Rome 3 By Sd in Mohammed Bin Rashid Al Maktoum District 11 is June 2028. At the last site inspection, in October 2026, it was 10% built. The developer is Samana Star Real Estate Development.
10%
Built, at the site inspection of 15 October 2026
Running behind its date
- Registered completion date
- June 2028
- Finish at recent pace
- June 2033
- Construction started
- July 2025
- First registered
- October 2025
- Developer
- Samana Star Real Estate Development
- Units
- 85
- Escrow bank
- Emirates NBD
- Name in Arabic
- روما 3 باي اس دي
- Project number
- 3459
- Site inspections
- 4
Schedule
Between February 2026 and October 2026 the site added about 1.1 points a month. At that rate it would finish around June 2033, more than three months after its registered date of June 2028.
Site inspections
15 October 2026
10%+7.8 pts
11 June 2026
2.4%+1.6 pts
3 February 2026
0.8%+0.8 pts
26 August 2025
0%
Context
Mohammed Bin Rashid Al Maktoum District 11 has 27 projects under construction, 29% built on average.
Samana Star Real Estate Development has 8 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Rome 3 By Sd?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Rome 3 By Sd handover date?
- The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Rome 3 By Sd?
- Rome 3 By Sd was 10% built at the site inspection on 15 October 2026. The site has been inspected 4 times since August 2025. The Land Department took 13 site photos at its inspections.
- Is Rome 3 By Sd delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Rome 3 By Sd?
- The registered developer is Samana Star Real Estate Development. It has 7 other projects under construction in Dubai.
- Which bank holds the escrow account for Rome 3 By Sd?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Manhattan 1 By SdAlso by Samana Star Real Estate Development. 30%.
- Manhattan 2 By SdAlso by Samana Star Real Estate Development. 21%, Due November 2026, passed.
- California 2 By SdAlso by Samana Star Real Estate Development. 34%, Due October 2026, passed.
- Ocean Pearl By SdAlso by Samana Star Real Estate Development. 25%, Due December 2026.
- The Waterside Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 45%, Due June 2026, passed.
- The Lakeview Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 20%, Due August 2026, passed.
- The Woodland ResidencesNearby in Mohammed Bin Rashid Al Maktoum District 11. 75%, Due April 2026, passed.
- The Beachfront Villas By EllingtonNearby in Mohammed Bin Rashid Al Maktoum District 11. 47%, Due August 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)