The Oasis - Palmiera 2 construction photos

53 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of The Oasis - Palmiera 2 was built on the day of each visit.

3 August 202677% built

21 April 202663% built

25 December 202553% built

25 September 202538% built

16 June 202528% built

24 March 202511% built

29 October 20241.8% built

1 April 20240.6% built

Back to The Oasis - Palmiera 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.