The Oasis - Palmiera 2 construction photos
53 photos taken by Dubai Land Department engineers at 8 site inspections, newest first. The percentage is how much of The Oasis - Palmiera 2 was built on the day of each visit.
3 August 202677% built
21 April 202663% built
25 December 202553% built
25 September 202538% built
16 June 202528% built
24 March 202511% built
29 October 20241.8% built
1 April 20240.6% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.