The Oasis - Mirage construction photos

39 photos from 7 site inspections, newest first. The percentage is how much of The Oasis - Mirage was built on the day of each visit.

29 June 202647% built

7 May 202631% built

11 November 202519% built

22 July 20255.2% built

3 March 20252.3% built

16 October 20241.7% built

1 April 20240.5% built

Back to The Oasis - Mirage construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.