Forest City Tower construction progress

Forest City Tower in Majan is 70% built at the Land Department inspection of August 2026. Developer Al Helal Al Zahaby Real Estate Development. Completion registered for April 2027.

70%

Built, at the Land Department site inspection of 13 August 2026

On pace for its date

Completion date (Land Department)
April 2027
Finish at recent pace
February 2027
Construction started
October 2024
Registered with the Land Department
November 2024
Community
Majan
Units
253
Escrow bank
Emirates Islamic Bank
Name in Arabic
فورست سيتي تاور
Land Department project number
3330
Land Department site inspections
6

Schedule

Since October 2025 Forest City Tower has added about 5.1 points a month. That puts 100% around February 2027, within three months of its registered completion date of April 2027.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 August 2026

70%+14 pts

  • Forest City Tower construction site, Land Department inspection photo 1, 13 August 2026
  • Forest City Tower construction site, Land Department inspection photo 2, 13 August 2026
  • Forest City Tower construction site, Land Department inspection photo 3, 13 August 2026
  • Forest City Tower construction site, Land Department inspection photo 4, 13 August 2026

8 May 2026

56%+19 pts

  • Forest City Tower construction site, Land Department inspection photo 1, 8 May 2026
  • Forest City Tower construction site, Land Department inspection photo 2, 8 May 2026
  • Forest City Tower construction site, Land Department inspection photo 3, 8 May 2026
  • Forest City Tower construction site, Land Department inspection photo 4, 8 May 2026

3 February 2026

37%+17 pts

  • Forest City Tower construction site, Land Department inspection photo 1, 3 February 2026
  • Forest City Tower construction site, Land Department inspection photo 2, 3 February 2026
  • Forest City Tower construction site, Land Department inspection photo 3, 3 February 2026
  • Forest City Tower construction site, Land Department inspection photo 4, 3 February 2026

24 October 2025

21%+7.7 pts

  • Forest City Tower construction site, Land Department inspection photo 1, 24 October 2025
  • Forest City Tower construction site, Land Department inspection photo 2, 24 October 2025
  • Forest City Tower construction site, Land Department inspection photo 3, 24 October 2025
  • Forest City Tower construction site, Land Department inspection photo 4, 24 October 2025

22 May 2025

13%+13 pts

  • Forest City Tower construction site, Land Department inspection photo 1, 22 May 2025
  • Forest City Tower construction site, Land Department inspection photo 2, 22 May 2025
  • Forest City Tower construction site, Land Department inspection photo 3, 22 May 2025
  • Forest City Tower construction site, Land Department inspection photo 4, 22 May 2025

24 October 2024

0%

  • Forest City Tower construction site, Land Department inspection photo 1, 24 October 2024
  • Forest City Tower construction site, Land Department inspection photo 2, 24 October 2024

All 48 site photos, by inspection date

Context

Majan has 25 projects under construction, 24% built on average.

Al Helal Al Zahaby Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Forest City Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Forest City Tower be completed?
The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around February 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Forest City Tower is built?
70%, measured at the Land Department site inspection on 13 August 2026. The Land Department engineers have inspected the site 6 times since October 2024.
Is Forest City Tower delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of April 2027.
Who is building Forest City Tower?
The registered developer is Al Helal Al Zahaby Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Forest City Tower?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.