Forest City Tower construction progress
The registered completion date for Forest City Tower in Majan is April 2027. At the last site inspection, in August 2026, it was 70% built. The developer is Al Helal Al Zahaby Real Estate Development.
70%
Built, at the site inspection of 13 August 2026
On pace for its date
- Registered completion date
- April 2027
- Finish at recent pace
- February 2027
- Construction started
- October 2024
- First registered
- November 2024
- Community
- Majan
- Units
- 253
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- فورست سيتي تاور
- Project number
- 3330
- Site inspections
- 6
Schedule
Since October 2025 Forest City Tower has added about 5.1 points a month. That puts 100% around February 2027, within three months of its registered completion date of April 2027.
Site inspections
13 August 2026
70%+14 pts
8 May 2026
56%+19 pts
3 February 2026
37%+17 pts
24 October 2025
21%+7.7 pts
22 May 2025
13%+13 pts
24 October 2024
0%
Context
Majan has 25 projects under construction, 28% built on average.
Al Helal Al Zahaby Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Forest City Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Forest City Tower handover date?
- The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Forest City Tower?
- Forest City Tower was 70% built at the site inspection on 13 August 2026. The site has been inspected 6 times since October 2024. The Land Department took 48 site photos at its inspections.
- Is Forest City Tower delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of April 2027.
- Who is building Forest City Tower?
- The registered developer is Al Helal Al Zahaby Real Estate Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Forest City Tower?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Oasis ResidencesAlso by Al Helal Al Zahaby Real Estate Development. 58%, Due July 2027.
- Forest City Tower 2Also by Al Helal Al Zahaby Real Estate Development. 1.2%, Due June 2027.
- Sports View Residence 2 By Al Helal Al ZahabyAlso by Al Helal Al Zahaby Real Estate Development. 26%, Due November 2029.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Samana Barari ViewsNearby in Majan. 32%, Due March 2027.
- Samana Barari Views 2Nearby in Majan. 26%.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)