Oasis Residences construction progress
The registered completion date for Oasis Residences in Dubai South Residential District is July 2027. At the last site inspection, in October 2026, it was 58% built. The developer is Al Helal Al Zahaby Real Estate Development.
58%
Built, at the site inspection of 30 October 2026
On pace for its date
- Registered completion date
- July 2027
- Finish at recent pace
- July 2027
- Construction started
- July 2025
- First registered
- August 2025
- Community
- Dubai South Residential District
- Units
- 159
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- اويسس ريسيدنسس
- Project number
- 3726
- Site inspections
- 5
Schedule
Since December 2025 Oasis Residences has added about 4.7 points a month. That puts 100% around July 2027, within three months of its registered completion date of July 2027.
Site inspections
30 October 2026
58%+23 pts
16 July 2026
35%+13 pts
23 March 2026
22%+13 pts
16 December 2025
9.1%+9.1 pts
15 May 2025
0%
Context
Dubai South Residential District has 37 projects under construction, 43% built on average.
Al Helal Al Zahaby Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Oasis Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Oasis Residences handover date?
- The registered completion date is July 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Oasis Residences?
- Oasis Residences was 58% built at the site inspection on 30 October 2026. The site has been inspected 5 times since May 2025. The Land Department took 34 site photos at its inspections.
- Is Oasis Residences delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of July 2027.
- Who is building Oasis Residences?
- The registered developer is Al Helal Al Zahaby Real Estate Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Oasis Residences?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Forest City TowerAlso by Al Helal Al Zahaby Real Estate Development. 70%, Due April 2027.
- Forest City Tower 2Also by Al Helal Al Zahaby Real Estate Development. 1.2%, Due June 2027.
- Sports View Residence 2 By Al Helal Al ZahabyAlso by Al Helal Al Zahaby Real Estate Development. 26%, Due November 2029.
- South Bay 1Nearby in Dubai South Residential District. 94%, Due March 2025, passed.
- South Bay 2Nearby in Dubai South Residential District. 94%, Due May 2026, passed.
- South Bay 3 PremiumNearby in Dubai South Residential District. 88%.
- South Bay 4 PremiumNearby in Dubai South Residential District. 86%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.