Forest City Tower 2 construction progress
The registered completion date for Forest City Tower 2 in Dubai Land Residence Complex is June 2027. At the last site inspection, in October 2026, it was 1.2% built. The developer is Al Helal Al Zahaby Real Estate Development.
1.2%
Built, at the site inspection of 15 October 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- September 2052
- Construction started
- June 2025
- First registered
- August 2025
- Community
- Dubai Land Residence Complex
- Units
- 194
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- فورست سيتي تاور 2
- Project number
- 3727
- Site inspections
- 3
Schedule
Between June 2026 and October 2026 the site added about 0.3 points a month. At that rate it would finish around September 2052, more than three months after its registered date of June 2027.
Site inspections
15 October 2026
1.2%+1.2 pts
26 June 2026
0%+0.0 pts
1 May 2025
0%
Context
Dubai Land Residence Complex has 63 projects under construction, 28% built on average.
Al Helal Al Zahaby Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Forest City Tower 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Forest City Tower 2 handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2052. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Forest City Tower 2?
- Forest City Tower 2 was 1.2% built at the site inspection on 15 October 2026. The site has been inspected 3 times since May 2025. The Land Department took 10 site photos at its inspections.
- Is Forest City Tower 2 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Forest City Tower 2?
- The registered developer is Al Helal Al Zahaby Real Estate Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Forest City Tower 2?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Forest City TowerAlso by Al Helal Al Zahaby Real Estate Development. 70%, Due April 2027.
- Oasis ResidencesAlso by Al Helal Al Zahaby Real Estate Development. 58%, Due July 2027.
- Sports View Residence 2 By Al Helal Al ZahabyAlso by Al Helal Al Zahaby Real Estate Development. 26%, Due November 2029.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026, passed.
- Ag SquareNearby in Dubai Land Residence Complex. 69%, Due September 2026, passed.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)