Forest City Tower 2 construction progress

The registered completion date for Forest City Tower 2 in Dubai Land Residence Complex is June 2027. At the last site inspection, in October 2026, it was 1.2% built. The developer is Al Helal Al Zahaby Real Estate Development.

1.2%

Built, at the site inspection of 15 October 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
September 2052
Construction started
June 2025
First registered
August 2025
Units
194
Escrow bank
Emirates Islamic Bank
Name in Arabic
فورست سيتي تاور 2
Project number
3727
Site inspections
3

Schedule

Between June 2026 and October 2026 the site added about 0.3 points a month. At that rate it would finish around September 2052, more than three months after its registered date of June 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

15 October 2026

1.2%+1.2 pts

  • Forest City Tower 2 construction site, inspection photo 1, 15 October 2026
  • Forest City Tower 2 construction site, inspection photo 2, 15 October 2026
  • Forest City Tower 2 construction site, inspection photo 3, 15 October 2026
  • Forest City Tower 2 construction site, inspection photo 4, 15 October 2026

26 June 2026

0%+0.0 pts

  • Forest City Tower 2 construction site, inspection photo 1, 26 June 2026
  • Forest City Tower 2 construction site, inspection photo 2, 26 June 2026
  • Forest City Tower 2 construction site, inspection photo 3, 26 June 2026

1 May 2025

0%

  • Forest City Tower 2 construction site, inspection photo 1, 1 May 2025
  • Forest City Tower 2 construction site, inspection photo 2, 1 May 2025

All 10 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Al Helal Al Zahaby Real Estate Development has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Forest City Tower 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Forest City Tower 2 handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2052. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Forest City Tower 2?
Forest City Tower 2 was 1.2% built at the site inspection on 15 October 2026. The site has been inspected 3 times since May 2025. The Land Department took 10 site photos at its inspections.
Is Forest City Tower 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Forest City Tower 2?
The registered developer is Al Helal Al Zahaby Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Forest City Tower 2?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.