Volga Tower construction photos
58 photos from 7 site inspections, newest first. The percentage is how much of Volga Tower was built on the day of each visit.
5 October 202651% built
25 June 202638% built
6 April 202634% built
29 December 202526% built
24 July 202518% built
20 February 202512% built
12 July 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.