Violet Tower construction progress

Violet Tower in Jumeirah Village Circle was registered to complete in June 2026 and is still under construction. At the last site inspection, in October 2026, it was 90% built. The developer is Dubai Investment Real Estate.

90%

Built, at the site inspection of 27 October 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
December 2026
Construction started
November 2023
First registered
February 2024
Units
287
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
فيوليت تاور
Project number
2824
Site inspections
7

Schedule

Violet Tower was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 4.8 points a month. Kept at that rate, the site would reach 100% around December 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 October 2026

90%+20 pts

  • Violet Tower construction site, inspection photo 1, 27 October 2026
  • Violet Tower construction site, inspection photo 2, 27 October 2026
  • Violet Tower construction site, inspection photo 3, 27 October 2026
  • Violet Tower construction site, inspection photo 4, 27 October 2026

9 June 2026

70%+15 pts

  • Violet Tower construction site, inspection photo 1, 9 June 2026
  • Violet Tower construction site, inspection photo 2, 9 June 2026
  • Violet Tower construction site, inspection photo 3, 9 June 2026
  • Violet Tower construction site, inspection photo 4, 9 June 2026

17 March 2026

55%+27 pts

  • Violet Tower construction site, inspection photo 1, 17 March 2026
  • Violet Tower construction site, inspection photo 2, 17 March 2026
  • Violet Tower construction site, inspection photo 3, 17 March 2026
  • Violet Tower construction site, inspection photo 4, 17 March 2026

7 October 2025

29%+8.4 pts

  • Violet Tower construction site, inspection photo 1, 7 October 2025
  • Violet Tower construction site, inspection photo 2, 7 October 2025
  • Violet Tower construction site, inspection photo 3, 7 October 2025
  • Violet Tower construction site, inspection photo 4, 7 October 2025

23 June 2025

20%+3.0 pts

  • Violet Tower construction site, inspection photo 1, 23 June 2025
  • Violet Tower construction site, inspection photo 2, 23 June 2025
  • Violet Tower construction site, inspection photo 3, 23 June 2025
  • Violet Tower construction site, inspection photo 4, 23 June 2025

8 May 2025

17%+17 pts

  • Violet Tower construction site, inspection photo 1, 8 May 2025
  • Violet Tower construction site, inspection photo 2, 8 May 2025
  • Violet Tower construction site, inspection photo 3, 8 May 2025
  • Violet Tower construction site, inspection photo 4, 8 May 2025

19 December 2023

0%

  • Violet Tower construction site, inspection photo 1, 19 December 2023
  • Violet Tower construction site, inspection photo 2, 19 December 2023
  • Violet Tower construction site, inspection photo 3, 19 December 2023

All 56 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Dubai Investment Real Estate has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Violet Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Violet Tower handover date?
The registered completion date was June 2026, and the register still lists Violet Tower as under construction. At the pace of its recent inspections the site would reach 100% around December 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Violet Tower?
Violet Tower was 90% built at the site inspection on 27 October 2026. The site has been inspected 7 times since December 2023. The Land Department took 56 site photos at its inspections.
Is Violet Tower delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Violet Tower?
The registered developer is Dubai Investment Real Estate. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Violet Tower?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.