Violet Tower construction progress
Violet Tower in Jumeirah Village Circle is 70% built at the Land Department inspection of June 2026. Developer Dubai Investment Real Estate. Completion registered for June 2026.
70%
Built, at the Land Department site inspection of 9 June 2026
3 months past its registered completion date
- Completion date (Land Department)
- June 2026
- Finish at recent pace
- January 2027
- Construction started
- November 2023
- Registered with the Land Department
- February 2024
- Developer
- Dubai Investment Real Estate
- Community
- Jumeirah Village Circle
- Units
- 287
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- فيوليت تاور
- Land Department project number
- 2824
- Land Department site inspections
- 6
Schedule
Violet Tower was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 4.4 points a month. Kept at that rate, the site would reach 100% around January 2027.
Site inspections
9 June 2026
70%+15 pts
17 March 2026
55%+27 pts
7 October 2025
29%+8.4 pts
23 June 2025
20%+3.0 pts
8 May 2025
17%+17 pts
19 December 2023
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Dubai Investment Real Estate has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Violet Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Violet Tower be completed?
- The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Violet Tower is built?
- 70%, measured at the Land Department site inspection on 9 June 2026. The Land Department engineers have inspected the site 6 times since December 2023.
- Is Violet Tower delayed?
- Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
- Who is building Violet Tower?
- The registered developer is Dubai Investment Real Estate. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Violet Tower?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mirdif Hills - Asayel AvenueAlso by Dubai Investment Real Estate. 33%, Due May 2027.
- Al VistaAlso by Dubai Investment Real Estate. 5.5%, Due October 2027.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)