Violet Tower construction progress

Violet Tower in Jumeirah Village Circle is 70% built at the Land Department inspection of June 2026. Developer Dubai Investment Real Estate. Completion registered for June 2026.

70%

Built, at the Land Department site inspection of 9 June 2026

3 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
January 2027
Construction started
November 2023
Registered with the Land Department
February 2024
Units
287
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
فيوليت تاور
Land Department project number
2824
Land Department site inspections
6

Schedule

Violet Tower was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 4.4 points a month. Kept at that rate, the site would reach 100% around January 2027.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

9 June 2026

70%+15 pts

  • Violet Tower construction site, Land Department inspection photo 1, 9 June 2026
  • Violet Tower construction site, Land Department inspection photo 2, 9 June 2026
  • Violet Tower construction site, Land Department inspection photo 3, 9 June 2026
  • Violet Tower construction site, Land Department inspection photo 4, 9 June 2026

17 March 2026

55%+27 pts

  • Violet Tower construction site, Land Department inspection photo 1, 17 March 2026
  • Violet Tower construction site, Land Department inspection photo 2, 17 March 2026
  • Violet Tower construction site, Land Department inspection photo 3, 17 March 2026
  • Violet Tower construction site, Land Department inspection photo 4, 17 March 2026

7 October 2025

29%+8.4 pts

  • Violet Tower construction site, Land Department inspection photo 1, 7 October 2025
  • Violet Tower construction site, Land Department inspection photo 2, 7 October 2025
  • Violet Tower construction site, Land Department inspection photo 3, 7 October 2025
  • Violet Tower construction site, Land Department inspection photo 4, 7 October 2025

23 June 2025

20%+3.0 pts

  • Violet Tower construction site, Land Department inspection photo 1, 23 June 2025
  • Violet Tower construction site, Land Department inspection photo 2, 23 June 2025
  • Violet Tower construction site, Land Department inspection photo 3, 23 June 2025
  • Violet Tower construction site, Land Department inspection photo 4, 23 June 2025

8 May 2025

17%+17 pts

  • Violet Tower construction site, Land Department inspection photo 1, 8 May 2025
  • Violet Tower construction site, Land Department inspection photo 2, 8 May 2025
  • Violet Tower construction site, Land Department inspection photo 3, 8 May 2025
  • Violet Tower construction site, Land Department inspection photo 4, 8 May 2025

19 December 2023

0%

  • Violet Tower construction site, Land Department inspection photo 1, 19 December 2023
  • Violet Tower construction site, Land Department inspection photo 2, 19 December 2023
  • Violet Tower construction site, Land Department inspection photo 3, 19 December 2023

All 44 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Dubai Investment Real Estate has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Violet Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Violet Tower be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around January 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Violet Tower is built?
70%, measured at the Land Department site inspection on 9 June 2026. The Land Department engineers have inspected the site 6 times since December 2023.
Is Violet Tower delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Violet Tower?
The registered developer is Dubai Investment Real Estate. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Violet Tower?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.