Al Vista construction progress
The registered completion date for Al Vista in Bukadra is October 2027. At the last site inspection, in October 2026, it was 9.5% built. The developer is Dubai Investment Real Estate.
9.5%
Built, at the site inspection of 28 October 2026
Running behind its date
- Registered completion date
- October 2027
- Finish at recent pace
- March 2034
- Construction started
- October 2025
- First registered
- November 2025
- Developer
- Dubai Investment Real Estate
- Community
- Bukadra
- Units
- 381
- Escrow bank
- Mashreq Bank
- Name in Arabic
- الفيستا
- Project number
- 3802
- Site inspections
- 3
Schedule
Between July 2026 and October 2026 the site added about 1.0 points a month. At that rate it would finish around March 2034, more than three months after its registered date of October 2027.
Site inspections
28 October 2026
9.5%+4.0 pts
1 July 2026
5.5%+5.5 pts
10 June 2025
0%
Context
Bukadra has 21 projects under construction, 27% built on average.
Dubai Investment Real Estate has 3 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Al Vista?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Al Vista handover date?
- The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Al Vista?
- Al Vista was 9.5% built at the site inspection on 28 October 2026. The site has been inspected 3 times since June 2025. The Land Department took 13 site photos at its inspections.
- Is Al Vista delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
- Who is building Al Vista?
- The registered developer is Dubai Investment Real Estate. It has 2 other projects under construction in Dubai.
- Which bank holds the escrow account for Al Vista?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Violet TowerAlso by Dubai Investment Real Estate. 90%, Due June 2026, passed.
- Mirdif Hills - Asayel AvenueAlso by Dubai Investment Real Estate. 33%, Due May 2027.
- 330 Riverside CrescentNearby in Bukadra. 68%.
- Sobha EstatesNearby in Bukadra. 68%, Due December 2027.
- 310 Riverside CrescentNearby in Bukadra. 50%.
- 360 Riverside CrescentNearby in Bukadra. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.