Al Vista construction progress

Al Vista in Bukadra is 5.5% built at the Land Department inspection of July 2026. Developer Dubai Investment Real Estate. Completion registered for October 2027.

5.5%

Built, at the Land Department site inspection of 1 July 2026

Running behind its date

Completion date (Land Department)
October 2027
Finish at recent pace
August 2044
Construction started
October 2025
Registered with the Land Department
November 2025
Community
Bukadra
Units
384
Escrow bank
Mashreq Bank
Name in Arabic
الفيستا
Land Department project number
3802
Land Department site inspections
2

Schedule

Between June 2025 and July 2026 the site added about 0.4 points a month. At that rate it would finish around August 2044, more than three months after the October 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 July 2026

5.5%+5.5 pts

  • Al Vista construction site, Land Department inspection photo 1, 1 July 2026
  • Al Vista construction site, Land Department inspection photo 2, 1 July 2026
  • Al Vista construction site, Land Department inspection photo 3, 1 July 2026
  • Al Vista construction site, Land Department inspection photo 4, 1 July 2026

10 June 2025

0%

  • Al Vista construction site, Land Department inspection photo 1, 10 June 2025
  • Al Vista construction site, Land Department inspection photo 2, 10 June 2025

All 7 site photos, by inspection date

Context

Bukadra has 21 projects under construction, 26% built on average.

Dubai Investment Real Estate has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Al Vista?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Al Vista be completed?
The completion date registered with the Dubai Land Department is October 2027. At the pace of its recent inspections the site would reach 100% around August 2044. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Al Vista is built?
5.5%, measured at the Land Department site inspection on 1 July 2026. The Land Department engineers have inspected the site 2 times since June 2025.
Is Al Vista delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Al Vista?
The registered developer is Dubai Investment Real Estate. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Al Vista?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.