Mirdif Hills - Asayel Avenue construction progress

Mirdif Hills - Asayel Avenue in Mirdif is 33% built at the Land Department inspection of May 2026. Developer Dubai Investment Real Estate. Completion registered for May 2027.

33%

Built, at the Land Department site inspection of 8 May 2026

Running behind its date

Completion date (Land Department)
May 2027
Finish at recent pace
September 2027
Construction started
May 2025
Registered with the Land Department
April 2025
Community
Mirdif
Units
193
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
مردف هيلز - اصايل افنيو
Land Department project number
3389
Land Department site inspections
3

Schedule

Between March 2026 and May 2026 the site added about 4.0 points a month. At that rate it would finish around September 2027, more than three months after the May 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

8 May 2026

33%+8.4 pts

  • Mirdif Hills - Asayel Avenue construction site, Land Department inspection photo 1, 8 May 2026
  • Mirdif Hills - Asayel Avenue construction site, Land Department inspection photo 2, 8 May 2026
  • Mirdif Hills - Asayel Avenue construction site, Land Department inspection photo 3, 8 May 2026
  • Mirdif Hills - Asayel Avenue construction site, Land Department inspection photo 4, 8 May 2026

6 March 2026

25%+25 pts

  • Mirdif Hills - Asayel Avenue construction site, Land Department inspection photo 1, 6 March 2026
  • Mirdif Hills - Asayel Avenue construction site, Land Department inspection photo 2, 6 March 2026
  • Mirdif Hills - Asayel Avenue construction site, Land Department inspection photo 3, 6 March 2026
  • Mirdif Hills - Asayel Avenue construction site, Land Department inspection photo 4, 6 March 2026

12 November 2024

0%

  • Mirdif Hills - Asayel Avenue construction site, Land Department inspection photo 1, 12 November 2024
  • Mirdif Hills - Asayel Avenue construction site, Land Department inspection photo 2, 12 November 2024

All 20 site photos, by inspection date

Context

Dubai Investment Real Estate has 3 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Mirdif Hills - Asayel Avenue?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Mirdif Hills - Asayel Avenue be completed?
The completion date registered with the Dubai Land Department is May 2027. At the pace of its recent inspections the site would reach 100% around September 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Mirdif Hills - Asayel Avenue is built?
33%, measured at the Land Department site inspection on 8 May 2026. The Land Department engineers have inspected the site 3 times since November 2024.
Is Mirdif Hills - Asayel Avenue delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Mirdif Hills - Asayel Avenue?
The registered developer is Dubai Investment Real Estate. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Mirdif Hills - Asayel Avenue?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.