Violet Tower construction photos
44 photos taken by Dubai Land Department engineers at 6 site inspections, newest first. The percentage is how much of Violet Tower was built on the day of each visit.
9 June 202670% built
17 March 202655% built
7 October 202529% built
23 June 202520% built
8 May 202517% built
19 December 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.