Terrazzo Residences construction photos
72 photos from 10 site inspections, newest first. The percentage is how much of Terrazzo Residences was built on the day of each visit.
27 July 202695% built
6 April 202684% built
3 December 202568% built
24 September 202559% built
17 June 202539% built
12 March 202520% built
4 November 20246.8% built
3 July 20240% built
13 December 20230% built
24 May 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.