Q Gardens Lofts 2 construction progress
Q Gardens Lofts 2 in Jumeirah Village Circle is 36% built at the Land Department inspection of September 2026. Developer A Y S Property Development.
36%
Built, at the Land Department site inspection of 17 September 2026
- Finish at recent pace
- September 2032
- Construction started
- February 2024
- Registered with the Land Department
- February 2024
- Developer
- A Y S Property Development
- Community
- Jumeirah Village Circle
- Units
- 221
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- 2 كيو جاردنز لوفتس
- Land Department project number
- 2677
- Land Department site inspections
- 8
Schedule
Since December 2025 Q Gardens Lofts 2 has added about 0.9 points a month. At that rate the site reaches 100% around September 2032. The Land Department has no completion date on record to compare it with.
Site inspections
17 September 2026
36%+6.3 pts
5 February 2026
30%+1.5 pts
23 December 2025
28%+0.6 pts
4 September 2025
27%+5.8 pts
23 April 2025
22%+11 pts
13 December 2024
11%+4.2 pts
10 October 2024
6.6%+6.6 pts
26 January 2024
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
A Y S Property Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Q Gardens Lofts 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Q Gardens Lofts 2 be completed?
- The Land Department has no completion date on record for Q Gardens Lofts 2 yet.
- How much of Q Gardens Lofts 2 is built?
- 36%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 8 times since January 2024.
- Who is building Q Gardens Lofts 2?
- The registered developer is A Y S Property Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Q Gardens Lofts 2?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Q Gardens LoftsAlso by A Y S Property Development. 91%, Due December 2025, passed.
- Q Gardens AliyaAlso by A Y S Property Development. 7.7%, Due June 2027.
- Tivanno ResidenceAlso by A Y S Property Development. 5.3%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)












.jpeg&w=3840&q=75)