Q Gardens Lofts construction progress

Q Gardens Lofts in Jumeirah Village Circle was registered to complete in December 2025 and is still under construction. At the last site inspection, in July 2026, it was 91% built. The developer is A Y S Property Development.

91%

Built, at the site inspection of 27 July 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
August 2027
Construction started
July 2022
First registered
October 2022
Units
194
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
كيو جاردنز لوفتس
Project number
2392
Site inspections
13

Schedule

Q Gardens Lofts was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 0.7 points a month. Kept at that rate, the site would reach 100% around August 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 July 2026

91%+1.7 pts

  • Q Gardens Lofts construction site, inspection photo 1, 27 July 2026
  • Q Gardens Lofts construction site, inspection photo 2, 27 July 2026
  • Q Gardens Lofts construction site, inspection photo 3, 27 July 2026
  • Q Gardens Lofts construction site, inspection photo 4, 27 July 2026

22 April 2026

89%+2.0 pts

  • Q Gardens Lofts construction site, inspection photo 1, 22 April 2026
  • Q Gardens Lofts construction site, inspection photo 2, 22 April 2026
  • Q Gardens Lofts construction site, inspection photo 3, 22 April 2026
  • Q Gardens Lofts construction site, inspection photo 4, 22 April 2026

23 December 2025

87%+3.8 pts

  • Q Gardens Lofts construction site, inspection photo 1, 23 December 2025
  • Q Gardens Lofts construction site, inspection photo 2, 23 December 2025
  • Q Gardens Lofts construction site, inspection photo 3, 23 December 2025
  • Q Gardens Lofts construction site, inspection photo 4, 23 December 2025

8 September 2025

83%+7.0 pts

  • Q Gardens Lofts construction site, inspection photo 1, 8 September 2025
  • Q Gardens Lofts construction site, inspection photo 2, 8 September 2025
  • Q Gardens Lofts construction site, inspection photo 3, 8 September 2025
  • Q Gardens Lofts construction site, inspection photo 4, 8 September 2025

23 April 2025

76%+5.9 pts

  • Q Gardens Lofts construction site, inspection photo 1, 23 April 2025
  • Q Gardens Lofts construction site, inspection photo 2, 23 April 2025
  • Q Gardens Lofts construction site, inspection photo 3, 23 April 2025
  • Q Gardens Lofts construction site, inspection photo 4, 23 April 2025

20 January 2025

70%+8.2 pts

  • Q Gardens Lofts construction site, inspection photo 1, 20 January 2025
  • Q Gardens Lofts construction site, inspection photo 2, 20 January 2025
  • Q Gardens Lofts construction site, inspection photo 3, 20 January 2025
  • Q Gardens Lofts construction site, inspection photo 4, 20 January 2025

10 October 2024

62%+13 pts

  • Q Gardens Lofts construction site, inspection photo 1, 10 October 2024
  • Q Gardens Lofts construction site, inspection photo 2, 10 October 2024
  • Q Gardens Lofts construction site, inspection photo 3, 10 October 2024
  • Q Gardens Lofts construction site, inspection photo 4, 10 October 2024

10 July 2024

49%+12 pts

  • Q Gardens Lofts construction site, inspection photo 1, 10 July 2024
  • Q Gardens Lofts construction site, inspection photo 2, 10 July 2024
  • Q Gardens Lofts construction site, inspection photo 3, 10 July 2024
  • Q Gardens Lofts construction site, inspection photo 4, 10 July 2024

15 April 2024

37%+12 pts

  • Q Gardens Lofts construction site, inspection photo 1, 15 April 2024
  • Q Gardens Lofts construction site, inspection photo 2, 15 April 2024
  • Q Gardens Lofts construction site, inspection photo 3, 15 April 2024
  • Q Gardens Lofts construction site, inspection photo 4, 15 April 2024

14 February 2024

25%+7.6 pts

  • Q Gardens Lofts construction site, inspection photo 1, 14 February 2024
  • Q Gardens Lofts construction site, inspection photo 2, 14 February 2024
  • Q Gardens Lofts construction site, inspection photo 3, 14 February 2024
  • Q Gardens Lofts construction site, inspection photo 4, 14 February 2024

All 105 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

A Y S Property Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Q Gardens Lofts?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Q Gardens Lofts handover date?
The registered completion date was December 2025, and the register still lists Q Gardens Lofts as under construction. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Q Gardens Lofts?
Q Gardens Lofts was 91% built at the site inspection on 27 July 2026. The site has been inspected 13 times since October 2022. The Land Department took 105 site photos at its inspections.
Is Q Gardens Lofts delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building Q Gardens Lofts?
The registered developer is A Y S Property Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Q Gardens Lofts?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.