Q Gardens Lofts construction progress
Q Gardens Lofts in Jumeirah Village Circle is 91% built at the Land Department inspection of July 2026. Developer A Y S Property Development. Completion registered for December 2025.
91%
Built, at the Land Department site inspection of 27 July 2026
9 months past its registered completion date
- Completion date (Land Department)
- December 2025
- Finish at recent pace
- August 2027
- Construction started
- July 2022
- Registered with the Land Department
- October 2022
- Developer
- A Y S Property Development
- Community
- Jumeirah Village Circle
- Units
- 194
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- كيو جاردنز لوفتس
- Land Department project number
- 2392
- Land Department site inspections
- 13
Schedule
Q Gardens Lofts was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 0.7 points a month. Kept at that rate, the site would reach 100% around August 2027.
Site inspections
27 July 2026
91%+1.7 pts
22 April 2026
89%+2.0 pts
23 December 2025
87%+3.8 pts
8 September 2025
83%+7.0 pts
23 April 2025
76%+5.9 pts
20 January 2025
70%+8.2 pts
10 October 2024
62%+13 pts
10 July 2024
49%+12 pts
15 April 2024
37%+12 pts
14 February 2024
25%+7.6 pts
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
A Y S Property Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Q Gardens Lofts?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Q Gardens Lofts be completed?
- The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around August 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Q Gardens Lofts is built?
- 91%, measured at the Land Department site inspection on 27 July 2026. The Land Department engineers have inspected the site 13 times since October 2022.
- Is Q Gardens Lofts delayed?
- Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
- Who is building Q Gardens Lofts?
- The registered developer is A Y S Property Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for Q Gardens Lofts?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Q Gardens Lofts 2Also by A Y S Property Development. 36%.
- Q Gardens AliyaAlso by A Y S Property Development. 7.7%, Due June 2027.
- Tivanno ResidenceAlso by A Y S Property Development. 5.3%.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.






.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)