Q Gardens Aliya construction progress

The registered completion date for Q Gardens Aliya in Jumeirah Village Circle is June 2027. At the last site inspection, in July 2026, it was 7.7% built. The developer is A Y S Property Development.

7.7%

Built, at the site inspection of 5 July 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
August 2843
Construction started
October 2024
First registered
October 2024
Units
278
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
كيو جاردنز عليا
Project number
3290
Site inspections
4

Schedule

Between December 2025 and July 2026 the site added about 0.0 points a month. At that rate it would finish around August 2843, more than three months after its registered date of June 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 July 2026

7.7%+0.1 pts

  • Q Gardens Aliya construction site, inspection photo 1, 5 July 2026
  • Q Gardens Aliya construction site, inspection photo 2, 5 July 2026
  • Q Gardens Aliya construction site, inspection photo 3, 5 July 2026
  • Q Gardens Aliya construction site, inspection photo 4, 5 July 2026

23 December 2025

7.6%+1.0 pts

  • Q Gardens Aliya construction site, inspection photo 1, 23 December 2025
  • Q Gardens Aliya construction site, inspection photo 2, 23 December 2025
  • Q Gardens Aliya construction site, inspection photo 3, 23 December 2025

15 May 2025

6.6%+6.6 pts

  • Q Gardens Aliya construction site, inspection photo 1, 15 May 2025
  • Q Gardens Aliya construction site, inspection photo 2, 15 May 2025
  • Q Gardens Aliya construction site, inspection photo 3, 15 May 2025
  • Q Gardens Aliya construction site, inspection photo 4, 15 May 2025

18 September 2024

0%

  • Q Gardens Aliya construction site, inspection photo 1, 18 September 2024
  • Q Gardens Aliya construction site, inspection photo 2, 18 September 2024
  • Q Gardens Aliya construction site, inspection photo 3, 18 September 2024

All 16 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

A Y S Property Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Q Gardens Aliya?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Q Gardens Aliya handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2843. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Q Gardens Aliya?
Q Gardens Aliya was 7.7% built at the site inspection on 5 July 2026. The site has been inspected 4 times since September 2024. The Land Department took 16 site photos at its inspections.
Is Q Gardens Aliya delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Q Gardens Aliya?
The registered developer is A Y S Property Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Q Gardens Aliya?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.