Q Gardens Lofts 2 construction photos

48 photos from 8 site inspections, newest first. The percentage is how much of Q Gardens Lofts 2 was built on the day of each visit.

17 September 202636% built

5 February 202630% built

23 December 202528% built

4 September 202527% built

23 April 202522% built

13 December 202411% built

10 October 20246.6% built

26 January 20240% built

Back to Q Gardens Lofts 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.