Q Gardens Lofts construction photos
105 photos from 13 site inspections, newest first. The percentage is how much of Q Gardens Lofts was built on the day of each visit.
27 July 202691% built
22 April 202689% built
23 December 202587% built
8 September 202583% built
23 April 202576% built
20 January 202570% built
10 October 202462% built
10 July 202449% built
15 April 202437% built
14 February 202425% built
12 October 202318% built
14 June 20239.3% built
10 October 20220% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.
.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)





.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)





.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)













































.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)


.jpg&w=3840&q=75)