Parkwood Residences construction photos

61 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of Parkwood Residences was built on the day of each visit.

18 September 202657% built

1 June 202652% built

5 February 202648% built

4 December 202546% built

1 August 202541% built

26 June 202540% built

17 January 202532% built

16 September 202429% built

20 March 202415% built

Back to Parkwood Residences construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.