Oxford Residence 2 construction progress

The register lists Oxford Residence 2 in Jumeirah Village Circle as complete, with a registered completion date of April 2020. Its last site inspection on record was in April 2020. The developer is Iman Developers.

100%

Built, at the site inspection of 27 April 2020

Construction complete

Registered completion date
April 2020
Construction started
June 2018
First registered
August 2018
Units
147
Escrow bank
Emirates NBD
Name in Arabic
2 اوكسفورد ريزيدينس
Project number
2080
Site inspections
4

Schedule

The register lists Oxford Residence 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 April 2020

100%+25 pts

  • Oxford Residence 2 construction site, inspection photo 1, 27 April 2020
  • Oxford Residence 2 construction site, inspection photo 2, 27 April 2020
  • Oxford Residence 2 construction site, inspection photo 3, 27 April 2020
  • Oxford Residence 2 construction site, inspection photo 4, 27 April 2020

1 October 2019

75%+17 pts

  • Oxford Residence 2 construction site, inspection photo 1, 1 October 2019
  • Oxford Residence 2 construction site, inspection photo 2, 1 October 2019
  • Oxford Residence 2 construction site, inspection photo 3, 1 October 2019
  • Oxford Residence 2 construction site, inspection photo 4, 1 October 2019

1 July 2019

58%+20 pts

  • Oxford Residence 2 construction site, inspection photo 1, 1 July 2019
  • Oxford Residence 2 construction site, inspection photo 2, 1 July 2019
  • Oxford Residence 2 construction site, inspection photo 3, 1 July 2019
  • Oxford Residence 2 construction site, inspection photo 4, 1 July 2019

28 February 2019

38%

  • Oxford Residence 2 construction site, inspection photo 1, 28 February 2019
  • Oxford Residence 2 construction site, inspection photo 2, 28 February 2019
  • Oxford Residence 2 construction site, inspection photo 3, 28 February 2019
  • Oxford Residence 2 construction site, inspection photo 4, 28 February 2019

All 45 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Iman Developers has 10 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Oxford Residence 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Oxford Residence 2 handover date?
Construction of Oxford Residence 2 is recorded as complete, with a registered completion date of April 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Oxford Residence 2?
Oxford Residence 2 was 100% built at the site inspection on 27 April 2020. The site has been inspected 4 times since February 2019. The Land Department took 45 site photos at its inspections.
Is Oxford Residence 2 delayed?
The register lists construction as complete.
Who is building Oxford Residence 2?
The registered developer is Iman Developers. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for Oxford Residence 2?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.