Skip to content

Oxford Residence construction progress

The register lists Oxford Residence in Jumeirah Village Circle as complete, with a registered completion date of February 2018. Its last site inspection on record was in June 2018. The developer is Iman Developers.

100%

Built, at the site inspection of 4 June 2018

Construction complete

Registered completion date
February 2018
Construction started
September 2016
First registered
April 2017
Units
103
Escrow bank
Emirates NBD
Name in Arabic
اوكسفورد رسيدانس
Project number
1881
Site inspections
3

Schedule

The register lists Oxford Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

4 June 2018

100%+24 pts

  • Oxford Residence construction site, inspection photo 1, 4 June 2018
  • Oxford Residence construction site, inspection photo 2, 4 June 2018
  • Oxford Residence construction site, inspection photo 3, 4 June 2018
  • Oxford Residence construction site, inspection photo 4, 4 June 2018

18 December 2017

76%+15 pts

  • Oxford Residence construction site, inspection photo 1, 18 December 2017
  • Oxford Residence construction site, inspection photo 2, 18 December 2017
  • Oxford Residence construction site, inspection photo 3, 18 December 2017
  • Oxford Residence construction site, inspection photo 4, 18 December 2017

17 August 2017

61%

  • Oxford Residence construction site, inspection photo 1, 17 August 2017
  • Oxford Residence construction site, inspection photo 2, 17 August 2017
  • Oxford Residence construction site, inspection photo 3, 17 August 2017
  • Oxford Residence construction site, inspection photo 4, 17 August 2017

All 21 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Iman Developers has 10 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Oxford Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Oxford Residence handover date?
Construction of Oxford Residence is recorded as complete, with a registered completion date of February 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Oxford Residence?
Oxford Residence was 100% built at the site inspection on 4 June 2018. The site has been inspected 3 times since August 2017. The Land Department took 21 site photos at its inspections.
Is Oxford Residence delayed?
The register lists construction as complete.
Who is building Oxford Residence?
The registered developer is Iman Developers. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for Oxford Residence?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.