Oxford Boulevard construction progress

The register lists Oxford Boulevard in Jumeirah Village Circle as complete, with a registered completion date of October 2021. Its last site inspection on record was in December 2021. The developer is Iman Developers.

100%

Built, at the site inspection of 29 December 2021

Construction complete

Registered completion date
October 2021
Construction started
October 2019
First registered
October 2020
Units
131
Escrow bank
Emirates NBD
Name in Arabic
أوكسفورد بوليوارد
Project number
2204
Site inspections
5

Schedule

The register lists Oxford Boulevard as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

29 December 2021

100%+1.5 pts

  • Oxford Boulevard construction site, inspection photo 1, 29 December 2021
  • Oxford Boulevard construction site, inspection photo 2, 29 December 2021
  • Oxford Boulevard construction site, inspection photo 3, 29 December 2021
  • Oxford Boulevard construction site, inspection photo 4, 29 December 2021

7 December 2021

98%+38 pts

  • Oxford Boulevard construction site, inspection photo 1, 7 December 2021
  • Oxford Boulevard construction site, inspection photo 2, 7 December 2021
  • Oxford Boulevard construction site, inspection photo 3, 7 December 2021
  • Oxford Boulevard construction site, inspection photo 4, 7 December 2021

28 March 2021

60%+19 pts

  • Oxford Boulevard construction site, inspection photo 1, 28 March 2021
  • Oxford Boulevard construction site, inspection photo 2, 28 March 2021
  • Oxford Boulevard construction site, inspection photo 3, 28 March 2021
  • Oxford Boulevard construction site, inspection photo 4, 28 March 2021

7 December 2020

41%+18 pts

  • Oxford Boulevard construction site, inspection photo 1, 7 December 2020
  • Oxford Boulevard construction site, inspection photo 2, 7 December 2020
  • Oxford Boulevard construction site, inspection photo 3, 7 December 2020
  • Oxford Boulevard construction site, inspection photo 4, 7 December 2020

19 March 2020

23%

  • Oxford Boulevard construction site, inspection photo 1, 19 March 2020
  • Oxford Boulevard construction site, inspection photo 2, 19 March 2020
  • Oxford Boulevard construction site, inspection photo 3, 19 March 2020
  • Oxford Boulevard construction site, inspection photo 4, 19 March 2020

All 52 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Iman Developers has 10 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Oxford Boulevard?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Oxford Boulevard handover date?
Construction of Oxford Boulevard is recorded as complete, with a registered completion date of October 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Oxford Boulevard?
Oxford Boulevard was 100% built at the site inspection on 29 December 2021. The site has been inspected 5 times since March 2020. The Land Department took 52 site photos at its inspections.
Is Oxford Boulevard delayed?
The register lists construction as complete.
Who is building Oxford Boulevard?
The registered developer is Iman Developers. It has 10 other projects under construction in Dubai.
Which bank holds the escrow account for Oxford Boulevard?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.