Maimoon Gardens construction progress
Maimoon Gardens in Jumeirah Village Circle was registered to complete in December 2025 and is still under construction. At the last site inspection, in November 2026, it was 81% built. The developer is Fakhruddin Properties Development.
81%
Built, at the site inspection of 16 November 2026
11 months past its registered completion date
- Registered completion date
- December 2025
- Finish at recent pace
- July 2027
- Construction started
- December 2022
- First registered
- August 2022
- Developer
- Fakhruddin Properties Development
- Community
- Jumeirah Village Circle
- Units
- 722
- Escrow bank
- Emirates NBD
- Name in Arabic
- ميمون جاردنز
- Project number
- 2412
- Site inspections
- 11
Schedule
Maimoon Gardens was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 2.4 points a month. Kept at that rate, the site would reach 100% around July 2027.
Site inspections
16 November 2026
81%+3.4 pts
13 August 2026
78%+15 pts
13 May 2026
63%+5.3 pts
22 January 2026
58%+16 pts
9 October 2025
42%+12 pts
20 February 2025
30%+7.7 pts
21 October 2024
22%+4.4 pts
17 July 2024
18%+9.8 pts
21 November 2023
8.2%+1.9 pts
14 June 2023
6.3%+4.3 pts
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Fakhruddin Properties Development has 6 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Maimoon Gardens?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Maimoon Gardens handover date?
- The registered completion date was December 2025, and the register still lists Maimoon Gardens as under construction. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Maimoon Gardens?
- Maimoon Gardens was 81% built at the site inspection on 16 November 2026. The site has been inspected 11 times since February 2023. The Land Department took 81 site photos at its inspections.
- Is Maimoon Gardens delayed?
- Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
- Who is building Maimoon Gardens?
- The registered developer is Fakhruddin Properties Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Maimoon Gardens?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Hatimi Residences By FakhruddinAlso by Fakhruddin Properties Development. 63%, Due October 2026, passed.
- Treppan TowerAlso by Fakhruddin Properties Development. 16%, Due April 2027.
- Treppan Serenique ResidencesAlso by Fakhruddin Properties Development. 5.2%, Due October 2027.
- Treppan Living PriveAlso by Fakhruddin Properties Development. 0%, Due December 2028.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)