Maimoon Gardens construction progress

Maimoon Gardens in Jumeirah Village Circle is 78% built at the Land Department inspection of August 2026. Developer Fakhruddin Properties Development. Completion registered for December 2025.

78%

Built, at the Land Department site inspection of 13 August 2026

9 months past its registered completion date

Completion date (Land Department)
December 2025
Finish at recent pace
February 2027
Construction started
December 2022
Registered with the Land Department
August 2022
Units
722
Escrow bank
Emirates NBD
Name in Arabic
ميمون جاردنز
Land Department project number
2412
Land Department site inspections
10

Schedule

Maimoon Gardens was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 3.5 points a month. Kept at that rate, the site would reach 100% around February 2027.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 August 2026

78%+15 pts

  • Maimoon Gardens construction site, Land Department inspection photo 1, 13 August 2026
  • Maimoon Gardens construction site, Land Department inspection photo 2, 13 August 2026
  • Maimoon Gardens construction site, Land Department inspection photo 3, 13 August 2026
  • Maimoon Gardens construction site, Land Department inspection photo 4, 13 August 2026

13 May 2026

63%+5.3 pts

  • Maimoon Gardens construction site, Land Department inspection photo 1, 13 May 2026
  • Maimoon Gardens construction site, Land Department inspection photo 2, 13 May 2026
  • Maimoon Gardens construction site, Land Department inspection photo 3, 13 May 2026
  • Maimoon Gardens construction site, Land Department inspection photo 4, 13 May 2026

22 January 2026

58%+16 pts

  • Maimoon Gardens construction site, Land Department inspection photo 1, 22 January 2026
  • Maimoon Gardens construction site, Land Department inspection photo 2, 22 January 2026
  • Maimoon Gardens construction site, Land Department inspection photo 3, 22 January 2026
  • Maimoon Gardens construction site, Land Department inspection photo 4, 22 January 2026

9 October 2025

42%+12 pts

  • Maimoon Gardens construction site, Land Department inspection photo 1, 9 October 2025
  • Maimoon Gardens construction site, Land Department inspection photo 2, 9 October 2025
  • Maimoon Gardens construction site, Land Department inspection photo 3, 9 October 2025
  • Maimoon Gardens construction site, Land Department inspection photo 4, 9 October 2025

20 February 2025

30%+7.7 pts

  • Maimoon Gardens construction site, Land Department inspection photo 1, 20 February 2025
  • Maimoon Gardens construction site, Land Department inspection photo 2, 20 February 2025
  • Maimoon Gardens construction site, Land Department inspection photo 3, 20 February 2025
  • Maimoon Gardens construction site, Land Department inspection photo 4, 20 February 2025

21 October 2024

22%+4.4 pts

  • Maimoon Gardens construction site, Land Department inspection photo 1, 21 October 2024
  • Maimoon Gardens construction site, Land Department inspection photo 2, 21 October 2024
  • Maimoon Gardens construction site, Land Department inspection photo 3, 21 October 2024
  • Maimoon Gardens construction site, Land Department inspection photo 4, 21 October 2024

17 July 2024

18%+9.8 pts

  • Maimoon Gardens construction site, Land Department inspection photo 1, 17 July 2024
  • Maimoon Gardens construction site, Land Department inspection photo 2, 17 July 2024
  • Maimoon Gardens construction site, Land Department inspection photo 3, 17 July 2024
  • Maimoon Gardens construction site, Land Department inspection photo 4, 17 July 2024

21 November 2023

8.2%+1.9 pts

  • Maimoon Gardens construction site, Land Department inspection photo 1, 21 November 2023
  • Maimoon Gardens construction site, Land Department inspection photo 2, 21 November 2023
  • Maimoon Gardens construction site, Land Department inspection photo 3, 21 November 2023
  • Maimoon Gardens construction site, Land Department inspection photo 4, 21 November 2023

14 June 2023

6.3%+4.3 pts

  • Maimoon Gardens construction site, Land Department inspection photo 1, 14 June 2023
  • Maimoon Gardens construction site, Land Department inspection photo 2, 14 June 2023
  • Maimoon Gardens construction site, Land Department inspection photo 3, 14 June 2023
  • Maimoon Gardens construction site, Land Department inspection photo 4, 14 June 2023

8 February 2023

2.0%

  • Maimoon Gardens construction site, Land Department inspection photo 1, 8 February 2023
  • Maimoon Gardens construction site, Land Department inspection photo 2, 8 February 2023
  • Maimoon Gardens construction site, Land Department inspection photo 3, 8 February 2023
  • Maimoon Gardens construction site, Land Department inspection photo 4, 8 February 2023

All 71 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Fakhruddin Properties Development has 6 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Maimoon Gardens?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Maimoon Gardens be completed?
The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around February 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Maimoon Gardens is built?
78%, measured at the Land Department site inspection on 13 August 2026. The Land Department engineers have inspected the site 10 times since February 2023.
Is Maimoon Gardens delayed?
Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
Who is building Maimoon Gardens?
The registered developer is Fakhruddin Properties Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Maimoon Gardens?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.