Skip to content

Treppan Serenique Residences construction progress

Treppan Serenique Residences in Palm Deira is 5.2% built at the Land Department inspection of July 2026. Developer Fakhruddin Properties Development. Completion registered for October 2027.

5.2%

Built, at the Land Department site inspection of 23 July 2026

Running behind its date

Completion date (Land Department)
October 2027
Construction started
October 2025
Registered with the Land Department
June 2025
Community
Palm Deira
Units
164
Escrow bank
Emirates NBD
Name in Arabic
تريبان سيرينيك ريزيدنسز
Land Department project number
3718
Land Department site inspections
3

Schedule

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 July 2026

5.2%

  • Treppan Serenique Residences construction site, Land Department inspection photo 1, 23 July 2026
  • Treppan Serenique Residences construction site, Land Department inspection photo 2, 23 July 2026
  • Treppan Serenique Residences construction site, Land Department inspection photo 3, 23 July 2026
  • Treppan Serenique Residences construction site, Land Department inspection photo 4, 23 July 2026

4 May 2026

5.2%+5.2 pts

  • Treppan Serenique Residences construction site, Land Department inspection photo 1, 4 May 2026
  • Treppan Serenique Residences construction site, Land Department inspection photo 2, 4 May 2026

2 May 2025

0%

  • Treppan Serenique Residences construction site, Land Department inspection photo 1, 2 May 2025
  • Treppan Serenique Residences construction site, Land Department inspection photo 2, 2 May 2025

All 8 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Fakhruddin Properties Development has 6 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Treppan Serenique Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Treppan Serenique Residences be completed?
The completion date registered with the Dubai Land Department is October 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Treppan Serenique Residences is built?
5.2%, measured at the Land Department site inspection on 23 July 2026. The Land Department engineers have inspected the site 3 times since May 2025.
Is Treppan Serenique Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Treppan Serenique Residences?
The registered developer is Fakhruddin Properties Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Treppan Serenique Residences?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.