Treppan Tower construction progress
The registered completion date for Treppan Tower in Jumeirah Village Triangle is April 2027. At the last site inspection, in November 2026, it was 16% built. The developer is Fakhruddin Properties Development.
16%
Built, at the site inspection of 10 November 2026
Running behind its date
- Registered completion date
- April 2027
- Finish at recent pace
- February 2031
- Construction started
- January 2025
- First registered
- December 2024
- Developer
- Fakhruddin Properties Development
- Community
- Jumeirah Village Triangle
- Units
- 263
- Escrow bank
- Emirates NBD
- Name in Arabic
- تريبان تاور
- Project number
- 3348
- Site inspections
- 4
Schedule
Between April 2026 and November 2026 the site added about 1.7 points a month. At that rate it would finish around February 2031, more than three months after its registered date of April 2027.
Site inspections
10 November 2026
16%+4.2 pts
7 August 2026
12%+7.2 pts
15 April 2026
4.7%+4.7 pts
24 October 2024
0%
Context
Jumeirah Village Triangle has 29 projects under construction, 27% built on average.
Fakhruddin Properties Development has 6 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Treppan Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Treppan Tower handover date?
- The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Treppan Tower?
- Treppan Tower was 16% built at the site inspection on 10 November 2026. The site has been inspected 4 times since October 2024. The Land Department took 13 site photos at its inspections.
- Is Treppan Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
- Who is building Treppan Tower?
- The registered developer is Fakhruddin Properties Development. It has 5 other projects under construction in Dubai.
- Which bank holds the escrow account for Treppan Tower?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Maimoon GardensAlso by Fakhruddin Properties Development. 81%, Due December 2025, passed.
- Hatimi Residences By FakhruddinAlso by Fakhruddin Properties Development. 63%, Due October 2026, passed.
- Treppan Serenique ResidencesAlso by Fakhruddin Properties Development. 5.2%, Due October 2027.
- Treppan Living PriveAlso by Fakhruddin Properties Development. 0%, Due December 2028.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Volga TowerNearby in Jumeirah Village Triangle. 51%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.