Treppan Tower construction progress

The registered completion date for Treppan Tower in Jumeirah Village Triangle is April 2027. At the last site inspection, in November 2026, it was 16% built. The developer is Fakhruddin Properties Development.

16%

Built, at the site inspection of 10 November 2026

Running behind its date

Registered completion date
April 2027
Finish at recent pace
February 2031
Construction started
January 2025
First registered
December 2024
Units
263
Escrow bank
Emirates NBD
Name in Arabic
تريبان تاور
Project number
3348
Site inspections
4

Schedule

Between April 2026 and November 2026 the site added about 1.7 points a month. At that rate it would finish around February 2031, more than three months after its registered date of April 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 November 2026

16%+4.2 pts

  • Treppan Tower construction site, inspection photo 1, 10 November 2026
  • Treppan Tower construction site, inspection photo 2, 10 November 2026
  • Treppan Tower construction site, inspection photo 3, 10 November 2026
  • Treppan Tower construction site, inspection photo 4, 10 November 2026

7 August 2026

12%+7.2 pts

  • Treppan Tower construction site, inspection photo 1, 7 August 2026
  • Treppan Tower construction site, inspection photo 2, 7 August 2026
  • Treppan Tower construction site, inspection photo 3, 7 August 2026
  • Treppan Tower construction site, inspection photo 4, 7 August 2026

15 April 2026

4.7%+4.7 pts

  • Treppan Tower construction site, inspection photo 1, 15 April 2026
  • Treppan Tower construction site, inspection photo 2, 15 April 2026

24 October 2024

0%

  • Treppan Tower construction site, inspection photo 1, 24 October 2024
  • Treppan Tower construction site, inspection photo 2, 24 October 2024

All 13 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Fakhruddin Properties Development has 6 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Treppan Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Treppan Tower handover date?
The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Treppan Tower?
Treppan Tower was 16% built at the site inspection on 10 November 2026. The site has been inspected 4 times since October 2024. The Land Department took 13 site photos at its inspections.
Is Treppan Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Treppan Tower?
The registered developer is Fakhruddin Properties Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Treppan Tower?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.