Treppan Tower construction progress

Treppan Tower in Jumeirah Village Triangle is 12% built at the Land Department inspection of August 2026. Developer Fakhruddin Properties Development. Completion registered for April 2027.

12%

Built, at the Land Department site inspection of 7 August 2026

Running behind its date

Completion date (Land Department)
April 2027
Finish at recent pace
June 2030
Construction started
January 2025
Registered with the Land Department
December 2024
Units
263
Escrow bank
Emirates NBD
Name in Arabic
تريبان تاور
Land Department project number
3348
Land Department site inspections
3

Schedule

Between April 2026 and August 2026 the site added about 1.9 points a month. At that rate it would finish around June 2030, more than three months after the April 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 August 2026

12%+7.2 pts

  • Treppan Tower construction site, Land Department inspection photo 1, 7 August 2026
  • Treppan Tower construction site, Land Department inspection photo 2, 7 August 2026
  • Treppan Tower construction site, Land Department inspection photo 3, 7 August 2026
  • Treppan Tower construction site, Land Department inspection photo 4, 7 August 2026

15 April 2026

4.7%+4.7 pts

  • Treppan Tower construction site, Land Department inspection photo 1, 15 April 2026
  • Treppan Tower construction site, Land Department inspection photo 2, 15 April 2026

24 October 2024

0%

  • Treppan Tower construction site, Land Department inspection photo 1, 24 October 2024
  • Treppan Tower construction site, Land Department inspection photo 2, 24 October 2024

All 9 site photos, by inspection date

Context

Jumeirah Village Triangle has 31 projects under construction, 28% built on average.

Fakhruddin Properties Development has 6 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Treppan Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Treppan Tower be completed?
The completion date registered with the Dubai Land Department is April 2027. At the pace of its recent inspections the site would reach 100% around June 2030. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Treppan Tower is built?
12%, measured at the Land Department site inspection on 7 August 2026. The Land Department engineers have inspected the site 3 times since October 2024.
Is Treppan Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Treppan Tower?
The registered developer is Fakhruddin Properties Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Treppan Tower?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.