Skip to content

Hatimi Residences By Fakhruddin construction progress

Hatimi Residences By Fakhruddin in Palm Deira was registered to complete in October 2026 and is still under construction. At the last site inspection, in November 2026, it was 63% built. The developer is Fakhruddin Properties Development.

63%

Built, at the site inspection of 6 November 2026

2 months past its registered completion date

Registered completion date
October 2026
Finish at recent pace
August 2027
Construction started
October 2024
First registered
April 2024
Community
Palm Deira
Units
116
Escrow bank
Emirates NBD
Name in Arabic
حاتمي ريزيدنس باي فخرالدين
Project number
2981
Site inspections
8

Schedule

Hatimi Residences By Fakhruddin was registered to complete in October 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 4.0 points a month. Kept at that rate, the site would reach 100% around August 2027.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 November 2026

63%+12 pts

  • Hatimi Residences By Fakhruddin construction site, inspection photo 1, 6 November 2026
  • Hatimi Residences By Fakhruddin construction site, inspection photo 2, 6 November 2026
  • Hatimi Residences By Fakhruddin construction site, inspection photo 3, 6 November 2026
  • Hatimi Residences By Fakhruddin construction site, inspection photo 4, 6 November 2026

4 August 2026

51%+11 pts

  • Hatimi Residences By Fakhruddin construction site, inspection photo 1, 4 August 2026
  • Hatimi Residences By Fakhruddin construction site, inspection photo 2, 4 August 2026
  • Hatimi Residences By Fakhruddin construction site, inspection photo 3, 4 August 2026
  • Hatimi Residences By Fakhruddin construction site, inspection photo 4, 4 August 2026

30 April 2026

40%+15 pts

  • Hatimi Residences By Fakhruddin construction site, inspection photo 1, 30 April 2026
  • Hatimi Residences By Fakhruddin construction site, inspection photo 2, 30 April 2026
  • Hatimi Residences By Fakhruddin construction site, inspection photo 3, 30 April 2026
  • Hatimi Residences By Fakhruddin construction site, inspection photo 4, 30 April 2026

14 January 2026

25%+17 pts

  • Hatimi Residences By Fakhruddin construction site, inspection photo 1, 14 January 2026
  • Hatimi Residences By Fakhruddin construction site, inspection photo 2, 14 January 2026
  • Hatimi Residences By Fakhruddin construction site, inspection photo 3, 14 January 2026
  • Hatimi Residences By Fakhruddin construction site, inspection photo 4, 14 January 2026

3 October 2025

7.8%+1.0 pts

  • Hatimi Residences By Fakhruddin construction site, inspection photo 1, 3 October 2025
  • Hatimi Residences By Fakhruddin construction site, inspection photo 2, 3 October 2025
  • Hatimi Residences By Fakhruddin construction site, inspection photo 3, 3 October 2025

10 March 2025

6.8%+6.8 pts

  • Hatimi Residences By Fakhruddin construction site, inspection photo 1, 10 March 2025
  • Hatimi Residences By Fakhruddin construction site, inspection photo 2, 10 March 2025

29 October 2024

0%+0.0 pts

  • Hatimi Residences By Fakhruddin construction site, inspection photo 1, 29 October 2024
  • Hatimi Residences By Fakhruddin construction site, inspection photo 2, 29 October 2024
  • Hatimi Residences By Fakhruddin construction site, inspection photo 3, 29 October 2024
  • Hatimi Residences By Fakhruddin construction site, inspection photo 4, 29 October 2024

25 March 2024

0%

  • Hatimi Residences By Fakhruddin construction site, inspection photo 1, 25 March 2024
  • Hatimi Residences By Fakhruddin construction site, inspection photo 2, 25 March 2024
  • Hatimi Residences By Fakhruddin construction site, inspection photo 3, 25 March 2024

All 45 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Fakhruddin Properties Development has 6 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Hatimi Residences By Fakhruddin?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Hatimi Residences By Fakhruddin handover date?
The registered completion date was October 2026, and the register still lists Hatimi Residences By Fakhruddin as under construction. At the pace of its recent inspections the site would reach 100% around August 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Hatimi Residences By Fakhruddin?
Hatimi Residences By Fakhruddin was 63% built at the site inspection on 6 November 2026. The site has been inspected 8 times since March 2024. The Land Department took 45 site photos at its inspections.
Is Hatimi Residences By Fakhruddin delayed?
Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
Who is building Hatimi Residences By Fakhruddin?
The registered developer is Fakhruddin Properties Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Hatimi Residences By Fakhruddin?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.