Hatimi Residences By Fakhruddin construction progress

Hatimi Residences By Fakhruddin in Palm Deira is 51% built at the Land Department inspection of August 2026. Developer Fakhruddin Properties Development. Completion registered for October 2026.

51%

Built, at the Land Department site inspection of 4 August 2026

0 months past its registered completion date

Completion date (Land Department)
October 2026
Finish at recent pace
July 2027
Construction started
October 2024
Registered with the Land Department
April 2024
Community
Palm Deira
Units
116
Escrow bank
Emirates NBD
Name in Arabic
حاتمي ريزيدنس باي فخرالدين
Land Department project number
2981
Land Department site inspections
7

Schedule

Hatimi Residences By Fakhruddin was registered to complete in October 2026, 1 month ago, and is still under construction. Over the last year of inspections it has added about 4.3 points a month. Kept at that rate, the site would reach 100% around July 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

4 August 2026

51%+11 pts

  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 1, 4 August 2026
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 2, 4 August 2026
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 3, 4 August 2026
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 4, 4 August 2026

30 April 2026

40%+15 pts

  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 1, 30 April 2026
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 2, 30 April 2026
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 3, 30 April 2026
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 4, 30 April 2026

14 January 2026

25%+17 pts

  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 1, 14 January 2026
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 2, 14 January 2026
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 3, 14 January 2026
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 4, 14 January 2026

3 October 2025

7.8%+1.0 pts

  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 1, 3 October 2025
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 2, 3 October 2025
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 3, 3 October 2025

10 March 2025

6.8%+6.8 pts

  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 1, 10 March 2025
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 2, 10 March 2025

29 October 2024

0%+0.0 pts

  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 1, 29 October 2024
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 2, 29 October 2024
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 3, 29 October 2024
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 4, 29 October 2024

25 March 2024

0%

  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 1, 25 March 2024
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 2, 25 March 2024
  • Hatimi Residences By Fakhruddin construction site, Land Department inspection photo 3, 25 March 2024

All 33 site photos, by inspection date

Context

Palm Deira has 95 projects under construction, 22% built on average.

Fakhruddin Properties Development has 6 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Hatimi Residences By Fakhruddin?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Hatimi Residences By Fakhruddin be completed?
The completion date registered with the Dubai Land Department is October 2026. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Hatimi Residences By Fakhruddin is built?
51%, measured at the Land Department site inspection on 4 August 2026. The Land Department engineers have inspected the site 7 times since March 2024.
Is Hatimi Residences By Fakhruddin delayed?
Yes. Its registered completion date of October 2026 has passed and the Land Department still lists it as under construction.
Who is building Hatimi Residences By Fakhruddin?
The registered developer is Fakhruddin Properties Development. It has 5 other projects under construction in Dubai.
Which bank holds the escrow account for Hatimi Residences By Fakhruddin?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.